As per CAN/ULC S801, on an electrical distribution overhead utility line circuit, verification of
voltage absence can be achieved by: - Using an approved voltage detector.
Isolation and tagging (no locks) is acceptable on an overhead distribution circuit under some of
the following conditions, E...
CUSP - T&D Questions & Answers As per CAN/ULC S801, on an electrical distribution overhead utility line circuit, verification of voltage absence can be achieved by: - ✔✔Using an approved voltage detector. Isolation and tagging (no locks) is acceptable on an overhead distribu tion circuit under some of the following conditions, EXCEPT for: - ✔✔The isolation can be operated from the ground directly at the base of a structure. Isolation and tagging (no locks) is acceptable for an overhead distribution circuit under some of the following conditions: - ✔✔1. The isolation point is a physical and visual like a line cut or riser removed. 2. The isolation point can only be operated by the operating authority or qualified worker. 3. The isolation point is protected from unauthorized access such as vertical height spacing. Consider that a circuit has been isolated, tagged and grounded. workers returning the next day must: - ✔✔Visually check grounds to verify they are in good order, secure and test for voltage. For lockout purposes, energy isolating devices shall be labelled or marked using a standardized nomenclature and format to indicate their function. Identification shall include: - ✔✔The equipment type, energy type, and magnit ude. Utilities often use a permitting system due to special circumstances of which conventional lockout is impracticable. The following is NOT a justified approach to this process: - ✔✔The isolation points are only simple single step actions. A high volt age utility or electrical company is authorized to use Complex Lockout (tag permitting) under what regulatory condition: - ✔✔A variance application has been approved by the provincial authority. Utilities often use a permitting system due to special circu mstances of which conventional lockout is impracticable. The following are justified approaches to this process: - ✔✔1. The isolation points are located in remote areas with difficult or restricted access. 2. The length of time to perform the lockout is im practicable. 3. Excessive numbers of persons required to lockout. Work on a distribution line must consider the following items when performing isolation and de -
energizing of the circuit.: - ✔✔1. Whether there are multiple sources of energy (loop feed) o n the circuit. 2. Is the line isolating device capable of interrupting load. 3. Is the line to be subject to inductive or capacitive charge. According to the CAN/ULC S801, what is the LEAST DESIRABLE type of fall protection: - ✔✔Fall Arrest System (FAS) Within Z259.14 standards fall restriction equipment (FRE) may only be leather in subcomponents or elements that are NOT exposed to: - ✔✔A dynamic load. As per Z259 standards, energy absorbing lanyards shall be classified according to their ability to absorb the kinetic energy from a fall as follows: - ✔✔Class E4 (4.0 kN) and Class E6 (6.0 kN) energy absorbing lanyards. Assuming that the fall protection system is correctly being used, in what scenario might the worker still contact the ground if they fell: - ✔✔Working 16 feet up in a bucket truck on distribution secondary services using a six foot shock absorbing lanyard, connected to the approved bucket anchor. What is NOT defined as a requirement of temporary vertical life lines as per Z259 standards: - ✔✔100% polypropylene fibers provide the greatest breaking strength. Requirements of temporary vertical life lines, as per Z259 standards: - ✔✔1. Shall be made from synthetic fibers with breaking strength of 27 kN or greater. 2. They shall be free of splices and knots, except at the terminations. 3. They shall be installed to protect against abrasion and sharp edges. Working on an energized lattice tower requires emergency response consistent with the associated hazards. What is NOT required as part of the emergency planning: - ✔✔Daily practice of tower rescue method.
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
√ Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, Bancontact of creditcard voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper Tulloch. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €15,61. Je zit daarna nergens aan vast.