QUESTION
According to AMSE B30.3 an overhead powerline is ALWAYS considered to be:
Answer:
Energized until the power company has verified it is not energized
QUESTION
High...
NCCCO Tower Crane Test (New 2023/ 2024
Update) Questions and Verified Answers|
Graded A| 100% Correct
QUESTION
According to AMSE B30.3 an overhead powerline is ALWAYS considered to be:
Answer:
Energized until the power company has verified it is not energized
QUESTION
High tensile bolts shall be marked with manufacturers designation and:
Answer:
Strength rating
QUESTION
Bolt connections for tower sections must use high tensile strength nuts with ratings of:
Answer:
12
QUESTION
Washers used in high tensile bolt connections shall be marked with:
Answer:
HV
,QUESTION
Before installation high tensile bolt connection Components shall be cleaned and visually
examined for:
Answer:
Damage and corrosion
QUESTION
When ready to torque the nut on a high tensile bolt connection you should:
Answer:
Lubricate threads
QUESTION
During tightening of high tensile connections the bolt is stretched to a specific percentage of its
elastic limit at the correct:
Answer:
Torque
QUESTION
Preferably the tightening torque shall be applied to the:
Answer:
Nut
QUESTION
The tightening torque values placed on the nuts and bolts of high tensile bolt connection are
dependent on the:
Answer:
Type and size
,QUESTION
What components of a tower crane are connected with high tensile bolt connections?
Answer:
Foundation anchors, tower sections, slewing ring support
QUESTION
When the Tower base bolts are torqued the counter jib should be positioned:
Answer:
0° from the bolt
QUESTION
According to the NCCCO tower crane reference manual what items below should be part of the
operators Daily pre-check?
Answer:
Wire ropes, limit switches
QUESTION
According to the NCCCO tower crane reference manual, how many safety turns (wraps) must
be left on the hoist drum when the load hook is in its lowest position?
Answer:
3
QUESTION
According to the NCCCO tower crane reference manual,when possible, installing the hoist wire
rope on a tower crane you should wind the rope with approximately how much of the maximum
permissible load?
, Answer:
10%
QUESTION
According to ASME B30.3, what is the design factor for rotation resistant load hoist wire rope?
Answer:
5.0 to 1
QUESTION
Who determines the correct hoist wire rope to be installed on tower cranes?
Answer:
Manufacturer
QUESTION
What grade alloy steel chain should be used for crane hoisting slings?
Answer:
80
QUESTION
According to ASME B30.3, using rotation resistant running rope on a tower crane, how many
broken wires in six rope diameters can you have to leave it in service?
Answer:
1
QUESTION
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
√ Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, Bancontact of creditcard voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper ace_it. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €10,77. Je zit daarna nergens aan vast.