ExAC - Section 4 - Bidding and Contract Negotiations, Construction Phase - Office, Construction Phase - Site, Project Management Questions with Correct Answers €15,20   In winkelwagen

Tentamen (uitwerkingen)

ExAC - Section 4 - Bidding and Contract Negotiations, Construction Phase - Office, Construction Phase - Site, Project Management Questions with Correct Answers

 7 keer bekeken  0 keer verkocht
  • Vak
  • Exac
  • Instelling
  • Exac

ExAC - Section 4 - Bidding and Contract Negotiations, Construction Phase - Office, Construction Phase - Site, Project Management Questions with Correct Answers

Voorbeeld 3 van de 29  pagina's

  • 17 augustus 2024
  • 29
  • 2024/2025
  • Tentamen (uitwerkingen)
  • Vragen en antwoorden
  • Exac
  • Exac
avatar-seller
ExAC - Section 4 - Bidding and Contract Negotiations,
Construction Phase - Office, Construction Phase - Site,
Project Management Questions with Correct Answers
List 6 types of project delivery methods and any respective CCDC
documents. Correct Answer-Design-Bid-Build (CCDC 2: Stip Sum,
CCDC 3: Cost Plus, CCDC 4: Unit Price)


Construction Management (CCDC 5A: CM Services, CCDC 5B: CM
Services and Work)


Design-Build (CCDC 14: Design Build Stip Sum, CCDC 15: Design
Builder/consultant contract (subcontract))


Public Private Partnership (P3) (No standard form of contract)


Single Purpose Entity for Integrated Project Delivery (not available in
Canada as of 2009)


List the advantages and disadvantages of Design-Bid-Build Projects
Correct Answer-Advantages:
-Widespread use/familiarity
-Clear roles assigned to each party
-Generally transparent process
-Thorough resolution of program requirements and design prior to
construction

,-Direct professional relationship between the client/building users and
the architect
-Known price prior to construction start


Disadvantages:
-Separation of Design and Construction restricts useful communication
-Clients sometimes perceive extras as being more prevalent and costly
under this form of of contract
-Contractor is unknown when CDs are prepared
-Contracts, particularly for public sector projects, usually awarded to
lowest bidder who may not be well qualified to do work.
Prequalification of contractors on public sector bids is not common.


What is Construction Management (as a form of project delivery)?
Correct Answer-Construction Management:
Broad term covering a variety of project delivery scenarios where a CM
is added to the design team early on to oversee: schedule, cost,
construction method, or building technology (could be an architect,
contractor, engineer, developer)


More common on large/complex projects because of added fee of
additional consultant. CM is not a licensed activity in most provinces


List 2 roles the Construction Manager can play (in CM project delivery).
Correct Answer-CM's can serve in different capacities with varying
degrees of authority:

, Advisor - during a particular phase


Manager of the construction of the project, with the owner contracting
directly with each trade contractor. CM may or may not be permitted to
assume responsibility for construction activities outlined in GC's of
specifications (ex temp facilities, site layout, clean-up).


List the advantages and disadvantages of Construction Management
Projects Correct Answer-Advantages:
-Direct contractual relationship with the Owner
-Construction advising during the design process
-Sequential bidding (saves time by permitting a start on construction
before all documentation is completed - fast track)
-Careful monitoring of costs and schedule:
Different checks and balances apply during design and construction
because the architect, trade contractors and CM are independent entities


Disadvantages:
-Construction usually commences before total costs are known
-Added cost/time for addition of additional consultant (CM)
-More complex relationships (traditional roles can be confused)
-Professional relationship between architect and owner and architect and
contractor now includes a third party (can sometimes complicate direct
communication)

Voordelen van het kopen van samenvattingen bij Stuvia op een rij:

√  	Verzekerd van kwaliteit door reviews

√ Verzekerd van kwaliteit door reviews

Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!

Snel en makkelijk kopen

Snel en makkelijk kopen

Je betaalt supersnel en eenmalig met iDeal, Bancontact of creditcard voor de samenvatting. Zonder lidmaatschap.

Focus op de essentie

Focus op de essentie

Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!

Veelgestelde vragen

Wat krijg ik als ik dit document koop?

Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.

Tevredenheidsgarantie: hoe werkt dat?

Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.

Van wie koop ik deze samenvatting?

Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper cracker. Stuvia faciliteert de betaling aan de verkoper.

Zit ik meteen vast aan een abonnement?

Nee, je koopt alleen deze samenvatting voor €15,20. Je zit daarna nergens aan vast.

Is Stuvia te vertrouwen?

4,6 sterren op Google & Trustpilot (+1000 reviews)

Afgelopen 30 dagen zijn er 81849 samenvattingen verkocht

Opgericht in 2010, al 14 jaar dé plek om samenvattingen te kopen

Start met verkopen
€15,20
  • (0)
  Kopen