100% tevredenheidsgarantie Direct beschikbaar na betaling Zowel online als in PDF Je zit nergens aan vast
Eerder door jou gezocht
ASPHALT PAVING LEVEL 1 AND LEVEL 2 EXAM STUDY GUIDE AND PRACTICE EXAM 2024/2025 | ACCURATE REAL EXAM QUESTIONS WITH VERIFIED ANSWERS | EXPERT VERIFIED FOR A GUARANTEED PASS | LATEST UPDATE€17,64
ASPHALT PAVING LEVEL 1 AND LEVEL 2 EXAM STUDY GUIDE AND PRACTICE EXAM 2024/2025 | ACCURATE REAL EXAM QUESTIONS WITH VERIFIED ANSWERS | EXPERT VERIFIED FOR A GUARANTEED PASS | LATEST UPDATE
29 keer bekeken 1 keer verkocht
Vak
ASPHALT PAVING LEVEL 1 AND LEVEL 2
Instelling
ASPHALT PAVING LEVEL 1 AND LEVEL 2
ASPHALT PAVING LEVEL 1 AND LEVEL 2 EXAM
STUDY GUIDE AND PRACTICE EXAM
2024/2025 | ACCURATE REAL EXAM
QUESTIONS WITH VERIFIED ANSWERS |
EXPERT VERIFIED FOR A GUARANTEED PASS |
LATEST UPDATE
asphalt paving level 1 and level 2 exam study guid
asphalt paving level 1 and level 2 exam study
Geschreven voor
ASPHALT PAVING LEVEL 1 AND LEVEL 2
ASPHALT PAVING LEVEL 1 AND LEVEL 2
Verkoper
Volgen
docwayne5
Ontvangen beoordelingen
Voorbeeld van de inhoud
ASPHALT PAVING LEVEL 1 AND LEVEL 2 EXAM
STUDY GUIDE AND PRACTICE EXAM
2024/2025 | ACCURATE REAL EXAM
QUESTIONS WITH VERIFIED ANSWERS |
EXPERT VERIFIED FOR A GUARANTEED PASS |
LATEST UPDATE
A full lot of super pave asphalt is what size?
1,000 tons
1,000 to 2000 tons
2000 to 4000 tons
1 days production - ✔✔ANSW✔✔..2000 to 4000 tons
Which is not typically used as an asphalt binder in fdot mix
designs?
PG 52-28
PG 58-22
PG 62-22
PG 76-22(PMA)
PG 82-22 (PMA) - ✔✔ANSW✔✔..PG 62-22
Who cuts the density cores used for verification testing?
The verification technician
The contractor
The independent verification testing technician
,None of the above - ✔✔ANSW✔✔..The contractor
A full lot is composed of 5 sublots and 4 cores per lot T/F -
✔✔ANSW✔✔..False
What is the most important for consistent compaction of asphalt
mix?
The mix is hotter in temperature
The mix is colder in temperature
The mix is uniform in temperature
Temperature of the mix does not affect compaction -
✔✔ANSW✔✔..The mix is uniform in temperature
Referring to general stationing guidelines, R1 would be ____ than
R2
Closer to centerline
Closer to outside shoulder
Closure to the inside shoulder
Both A and C - ✔✔ANSW✔✔..Both A and C
While using the rolling straightedge, if the needle goes in the red
zone indicating an unacceptable high spot in the section, you then
- ✔✔ANSW✔✔..Mark the pavement where the needle first goes
into the red zone and place another mark where the needle
leaves the red zone and continue
For bridge approach slabs, the 15 foot manual straightedge
should be set so ____ is on the bridge deck.
1 inch
Exactly 1/2 of the straightedge
The entire straightedge
None of the above - ✔✔ANSW✔✔..1 inch
, For the first transverse joint on a project place the ___ on the new
pavement while overlapping the transverse joint by one inch.
4 foot level
15 foot manual straight edge
Rolling straightedge
All the above - ✔✔ANSW✔✔..15 foot manual straight edge
When calibrating to check the low side of the rolling straight edge:
Place shims under the outer wheels
Place the rolling straight edge on a surface that looks flat
Place a 3/16 inch shin under each outside wheel, the gauge
should read zero on both sides of the gauge
Place shims under the center wheel - ✔✔ANSW✔✔..Place a 3/16
inch shin under each outside wheel, the gauge should read zero
on both sides of the gauge
When calibrating to check the high side of the rolling straight
edge:
Place shims under the outer wheels
Place shims under the center wheel
Place the rolling straight edge on a surface that looks flat
Place a 3/16 inch shin under the center wheel. The gauge should
read zero on both sides of the gauge. - ✔✔ANSW✔✔..Place a
3/16 inch shim under the center wheel. The gauge should read
zero on both sides of the gauge.
What do you need to know when manually checking the cross
slope?
The level length
The lane width
Height from the end of the level to pavement surface
The diameter of the bubble in the level - ✔✔ANSW✔✔..Level
length and height from the end of level to pavement surface
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
√ Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, Bancontact of creditcard voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper docwayne5. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €17,64. Je zit daarna nergens aan vast.