PMP RITA
Yale University
All 31 results
Sort by
-
Rita Mulcahy Examen PMP - Gestión del Alcance questions and answers
- Exam (elaborations) • 2 pages • 2023
-
- $16.99
- + learn more
UNO 
 
 
 
DOS 
 
 
 
TRES 
 
 
 
CUATRO 
 
 
 
CINCO 
 
 
 
SEIS 
 
 
 
SIETE 
 
 
 
OCHO 
 
 
 
NUEVE 
 
 
 
DIEZ 
 
 
 
B. Pedir al cliente una descripción del cambio. 
11. El proyecto esta casi finalizado. El proyecto tiene una variación del cronograma de 300 y una variación de coste de -900. Todas las inspecciones de control de calidad se han finalizado, salvo una, y todas han alcanzado los requisitos de calidad. Todas las acciones en el registro de polémicas se han resuelto. Muchos de ...
-
PMP RMC HT book 9th Schedule Management 2 with 100% correct answers
- Exam (elaborations) • 6 pages • 2023
-
- $15.49
- + learn more
Use the project scope statement to gain approval of the "final" scope from the stakeholders before further planning is done 
Planning 
 
 
 
Determine high-level requirements, constraints, assumptions, and risks 
Initiating 
 
 
 
Implement approved changes, including corrective actions, preventive actions, and defect repair 
Executing 
 
 
 
Reanalyze existing risks 
Monitoring & Controlling 
 
 
 
Use the high-level planning and estimating data to determine whether the product can be achieve...
-
PMP RMC HT book 9th Project Management Framework
- Exam (elaborations) • 5 pages • 2023
-
- $14.99
- + learn more
What is the definition of a project? 
Temporary endeavor—with a beginning and an end 
Creates a unique product, service, or result 
 
 
 
What is operational work? 
Ongoing work to support the business and systems of the organization 
 
 
 
What is the definition of a program? What is the definition of a portfolio? 
Program: A group of related projects, managed in a coordinated way 
Portfolio: A group of programs, individual projects, and other related operational work that are prioritized and...
-
PMP-RMC Super Exam-3 Failed questions with complete solutions.
- Exam (elaborations) • 11 pages • 2023
-
- $14.99
- + learn more
(33)* Question ID: 483 
As per the chart, the team member completing activity E is not performing very well. After much argument, the functional manager agrees to assign a different person to activity E, but this will increase activity E's duration to seven months. What is the effect of this change? 
 
A. The project will be delayed because activity E is on the critical path. 
B. None, because activity E is not on the critical path. 
C. None, because activity E has float of four. 
D. The projec...
-
PMP-RMC Super Exam-2 Failed questions and answers
- Exam (elaborations) • 47 pages • 2023
-
- $14.49
- + learn more
(1)* Question ID: 200 
Your project team has identified dependencies on six related projects that are providing major deliverables to your project. Some of these projects have a very similar scope and may overlap with your deliverables. In light of this, which of the following processes should you be most concerned about? 
 
A. Validate Scope 
B. Plan Risk Responses 
C. Plan Communications Management 
D. Control Scope 
The correct answer is B. 
 
The biggest concern must be the risks other proje...
Fear of missing out? Then don’t!
-
PMP Mock Exam 2023 with 100% correct answers(verified for accuracy).
- Exam (elaborations) • 47 pages • 2023
-
- $14.99
- + learn more
Shadi is working as a project manager of a software development project. The project is following a Scrum methodology. In the daily scrum meeting, the development team always comes to meetings late. Which of the following is most likely to be the cause of this problem? 
A. The team resents the work that they're doing. 
 
B. The team is in the storming phase of team development. 
 
*C. The project manager was late to meetings himself, and this influenced the team.* 
 
D. The project manager need...
-
PMP-RMC Super Exam-3 Failed questions and answers
- Exam (elaborations) • 11 pages • 2023
-
Available in package deal
-
- $14.99
- + learn more
(33)* Question ID: 483 
As per the chart, the team member completing activity E is not performing very well. After much argument, the functional manager agrees to assign a different person to activity E, but this will increase activity E's duration to seven months. What is the effect of this change? 
 
A. The project will be delayed because activity E is on the critical path. 
B. None, because activity E is not on the critical path. 
C. None, because activity E has float of four. 
D. The projec...
-
PMP Prep (RMC 8th Ed.) - Complete PM Process with 100% correct answersPMP Prep (RMC 8th Ed.) with 100% correct answers
- Exam (elaborations) • 8 pages • 2023
-
Available in package deal
-
- $15.49
- + learn more
Select PM 
Initiating1 
 
 
 
Determine company culture and existing systems 
Initiating2 
 
 
 
Collect processes, procedures, and historical information 
Initiating3 
 
 
 
Divide large projects into phases 
Initiating4 
 
 
 
Understand the business case 
Initiating5 
 
 
 
Uncover initial requirements, assumptions, risks, constraints, and existing agreements 
Initiating6 
 
 
 
Assess project and product feasibility within the given contsraints 
Initiating7 
 
 
 
Create measurable objects 
...
-
RMC College Knowledge 2023-2024 with verified correct answers
- Exam (elaborations) • 7 pages • 2023
-
Available in package deal
-
- $16.99
- + learn more
1 Squadron Name, Flight, Colour, Mascot 
Hudson, Alpha, Navy Blue, Spider 
 
 
 
2 Squadron Name, Flight, Colour, Mascot 
Lasalle, Fighter, Red, Griffon 
 
 
 
3 Squadron Name, Flight, Colour, Mascot 
Pontiac, Grizzly, Forest Green, Grizzly Bear 
 
 
 
4 Squadron Name, Flight, Colour, Mascot 
Frontenac, Keable, Sky Blue, Shark 
 
 
 
5 Squadron Name, Flight, Colour, Mascot 
Brock, Papa, Maroon, Phoenix 
 
 
 
6 Squadron Name, Flight, Colour, Mascot 
Brant, Romeo, Gold, Pirate 
 
 
 
7 Squadron N...
-
PMP 2023 EXAM STUDY GUIDE WITH 100% CORRECT ANSWERS
- Exam (elaborations) • 197 pages • 2023
-
Available in package deal
-
- $14.49
- + learn more
Question: 1 
 
A project is approaching successful completion, and all stakeholders are really proud of the 
achieved results. The project management office 
(PMO) recommends the project manager to lead the next similar project. 
What should the project manager do next? 
A. Engage key stakeholders to complete and deliver lessons learned. 
B. Select the same stakeholders for the next project to avoid doing knowledge transfer. 
C. Present the project achievements and delegate knowledge transfer to...
Do you wonder why so many students wear nice clothes, have money to spare and enjoy tons of free time? Well, they sell on Stuvia! Imagine your study notes being downloaded a dozen times for $15 each. Every. Single. Day. Discover all about earning on Stuvia