ACQ 1010
National Defense University
All 29 results
Sort by
-
ACQ 1010 MODULE 2 to 9 with All chapters Questions And Answers. Exam (elaborations)100% CORRECT
- Package deal • 8 items • 2024
-
- $28.49
- 1x sold
- + learn more
ACQ 1010 MODULE 2 to 9 with All chapters Questions And Answers. Exam (elaborations)100% CORRECT
-
ACQ 1010 Module 3 Exam_Defense Acquisition System ALREADY GRADED A+ (LATEST VERSION
- Exam (elaborations) • 3 pages • 2023
-
- $10.49
- + learn more
ACQ 1010 MODULE 3 EXAM: DEFENSE ACQUISITION SYSTEM 
What decision authorizes entry into the Production and Deployment phase? 
Answer: Milestone C decision 
Before a project enters the TMRR phase, the AoA must be completed and the Acquisition 
Strategy (AS) is approved by the MDA. 
Answer: True 
The Acquisition Strategy (AS) is: 
Answer: Prepared by the Program Manager (PM) during the Materiel Solution Analysis Phase (MSA) and is submitted 
to the Milestone Decision Authority (MDA) at Milestone A...
-
ACQ 1010 Module 2 Exam_Joint Capabilities Integration and Development System
- Exam (elaborations) • 1 pages • 2022
-
- $8.49
- + learn more
ACQ 1010 MODULE 2 EXAM: JOINT CAPABILITIES INTEGRATION AND DEVELOPMENT SYSTEM 
Assuring that material approaches are refined and key technologies are being matured, 
what JCIDS document is used to build upon the Initial Capabilities Document (ICD)? 
Answer: Capability Development Document (CDD) 
What is the purpose of a Capabilities Based-Assessment (CBA)? 
Answer: To analyze the military's capability needs and gaps and recommend both materiel and non-materiel solutions
-
ACQ 1010 Module 3 Exam_Defense Acquisition System.
- Exam (elaborations) • 3 pages • 2022
-
- $8.49
- + learn more
ACQ 1010 MODULE 3 EXAM: DEFENSE ACQUISITION SYSTEM 
What decision authorizes entry into the Production and Deployment phase? 
Answer: Milestone C decision 
Before a project enters the TMRR phase, the AoA must be completed and the Acquisition 
Strategy (AS) is approved by the MDA. 
Answer: True 
The Acquisition Strategy (AS) is: 
Answer: Prepared by the Program Manager (PM) during the Materiel Solution Analysis Phase (MSA) and is submitted 
to the Milestone Decision Authority (MDA) at Milestone A...
-
ACQ 1010 Module 6 Exam_Contract Management
- Exam (elaborations) • 1 pages • 2022
-
- $8.49
- + learn more
ACQ 1010 MODULE 6 EXAM: CONTRACT MANAGEMENT 
What is one purpose of contract administration? 
Answer: Avoiding or eliminating overlap and duplication of Government contract administration effort 
Which of the following describes an Indefinite-Quantity contract? 
Answer: Provides an indefinite quantity, within stated limits, of supplies or services to be furnished during a fixed 
period, within stated limits 
Who oversees the source selection process and selects the source whose proposal is 
the ...
As you read this, a fellow student has made another $4.70
-
ACQ 1010 Module 5 Exam_Financial Management
- Exam (elaborations) • 2 pages • 2022
-
- $8.49
- + learn more
ACQ 1010 MODULE 5 EXAM: FINANCIAL MANAGEMENT 
Below Threshold Reprogramming for procurement is limited to the lesser of $20 million 
or 20%, into or out of a program. Thresholds vary by appropriations category. 
Incorrect Answer: True 
Approval for reprogramming must always involve Congress. 
Incorrect Answer: True 
Which major appropriations category below is NOT included in the Life Cycle Cost 
Estimate? 
Answer: Investment 
Select the term that best fits the following definition: “The legal...
-
ACQ 1010 Module 7 Exam_Engineering Disciplines.
- Exam (elaborations) • 2 pages • 2022
-
- $8.49
- + learn more
ACQ 1010 MODULE 7 EXAM: ENGINEERING DISCIPLINES 
Which systems engineering supporting discipline has the goal to compare a system or 
components against requirements and specifications? 
Answer: test and evaluation 
The item detail specification, in combination with associated drawings, parts lists, 
process specs, and material specs, are together often referred to as the Technical Data 
Package (TDP). 
Answer: True 
In which phase are systems-level requirements stabilized and detailed designs 
...
-
ACQ 1010 Module 8 Exam_Test and Evaluation Overview.
- Exam (elaborations) • 1 pages • 2022
-
- $9.49
- + learn more
ACQ 1010 MODULE 8 EXAM: TEST AND EVALUATION OVERVIEW 
The Test and Evaluation Master Plan (TEMP) must be developed prior to which of the 
following? 
Answer: Milestone A and updated before each subsequent review 
Test and Evaluation (T&E) is used to identify technical risk, verify performance, and 
validate system utility throughout the defense system acquisition life cycle
-
ACQ 1010 Module 10 Exam_Intelligence Counter Intelligence Support & Resources.d
- Exam (elaborations) • 1 pages • 2022
-
- $8.29
- + learn more
ACQ 1010 MODULE 10 EXAM: INTELLIGENCE/COUNTER INTELLIGENCE SUPPORT & RESOURCES 
Which of the following organizations provides centralized management of DoD CI 
activities? 
Answer: Director, Defense Intelligence Agency (DIA) 
Counterintelligence (CI) organizations need information that describes the CPI and its 
projected use to determine the foreign collection threat to an acquisition program and 
subsequently the ______________. 
Answer: program acquisition strategy 
CIPS are _________________...
-
ACQ 1010 Module 9 Exam Life Cycle Logistics docx
- Exam (elaborations) • 2 pages • 2022
-
- $8.49
- + learn more
ACQ 1010 MODULE 9 EXAM: LIFE CYCLE LOGISTICS 
Performance Based Logistics (PBL) is based on long term Warfighter-driven thinking. 
Answer: True 
Life cycle consist of research and development costs, investment costs, operating and 
support costs, and disposal costs over the entire life cycle. 
Answer: True 
Which of the following best describes Performance Based Logistics contracts? 
Incorrect Answer: PBL Contracts allow the Product Support Provider (PSP) little flexibility on how they provide t...
How did he do that? By selling his study resources on Stuvia. Try it yourself! Discover all about earning on Stuvia