1. One common way to compute estimate at completion (EAC) is to take the budget at completion (BAC) and: A. Divide by SPI B. Multiply by SPI C. Multiply by CPI D. Divide by CPI Answer D This question is asking for the formula for EAC, which is BAC/CPI. Notice how you will have to remembe...