100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
CAPM Practice Exam – Quiz: Questions And Answers CA$27.92   Add to cart

Exam (elaborations)

CAPM Practice Exam – Quiz: Questions And Answers

 3 views  0 purchase

CAPM Practice Exam – Quiz: Questions And Answers

Preview 3 out of 24  pages

  • December 13, 2023
  • 24
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
All documents for this subject (35)
avatar-seller
Studycafe
CAPM Practice Exam – Quiz: Questions And
Answers
What other dependency types are possible in a project apart from internal and
external dependencies? Correct Ans ➡ Mandatory and discretionary

Which of the below can be the reasons for raising and processing a change
request?
A Corrective and preventive actions
B Updates to controlled documents (like baselines and plans) and deliverables
C Defect fixes
D All of the above Correct Ans ➡ All of the above

In which process are risks prioritized for further analysis or action by
assessing their probability, impact and other characteristics? Correct Ans
➡ Perform qualitative risk analysis

Identify the two techniques which are unique to the Manage Knowledge
process? Correct Ans ➡ Knowledge management and information
management

In what organizational structure type is the project manager's role full time?
Correct Ans ➡ Project-oriented

When defining project scope, techniques like systems/value engineering and
analysis are used. These are collectively known as: Correct Ans ➡
Product analysis

Procurement documents, procurement strategy, bid documents, procurement
SOW, source selection criteria, make-or-buy decisions and independent cost
estimates are outputs of which process? Correct Ans ➡ Plan
procurement management

Prioritization and allocation of resources in an organization is an objective of:
Correct Ans ➡ Portfolio management

Which of the below describes the 100% rule of WBS?
A The WBS should include all the project and product work

,B The WBS should not include any work which is not part of the project or
product work
CA&B
D None of the above Correct Ans ➡ C

Stakeholder analysis technique is used in which process for the first time?
Correct Ans ➡ Identify Stakeholders

There are two outputs from the Plan Scope Management process. One of them
is Scope Management Plan. Which is the other one? Correct Ans ➡
Requirements management plan

An activity is most likely expected to take 7 days. The maximum duration is
expected to be 10 days and the minimum 5 days. Calculate the expected
duration for this activity. Correct Ans ➡ 7.16 days

Which risk response strategies are used only to respond to threats? Correct
Ans ➡ Avoid, mitigate

The three factors namely management elements, governance frameworks and
organizational structures which interact and determine the power, influence,
interests, competence and political capabilities of the people in an
organization, are together known as: Correct Ans ➡ An organizational
system

An output of the Monitor and Control Project Work process is: Correct Ans
➡ Work performance report

Which of the below is not one of the three skills listed for a project manager as
per PMI Talent Triangle®? Correct Ans ➡ Technology management

In the Manage Communications process, project information is collected and
distributed as per the format and level of detail desired by stakeholders. What
is the name of this technique? Correct Ans ➡ Project reporting

In which process group a new project or phase is defined and authorization is
given to start it? Correct Ans ➡ Initiating

, A project has activities A,B,C,D and E with durations 3,5,7,2 and 4 days
respectively. A and B are started together. When A and B both are completed,
C and E are started together. When C finishes, D is performed. When B is
completed, E is performed. When both D and E are done, the project is
completed. What is the total float for activity E? Correct Ans ➡ 5 days

Two of the resource optimization techniques are: Correct Ans ➡
Resource levelling and resource smoothing

In general, who focuses on systems and structure and who on relationships
with people? Correct Ans ➡ Manager and leader respectively

Funding limit reconciliation is a technique in which process? Correct Ans
➡ Determine budget

What-if scenario analysis and simulation are techniques under which process
of project schedule management? Correct Ans ➡ Develop schedule,
control schedule

Which of the following will not be described in the scope management plan?
Correct Ans ➡ Detailed project and product scope

Reviewing changes between desired and current stakeholder engagement
levels, and adjusting communications as necessary is best done by which
technique in the Control Communications process? Correct Ans ➡
Stakeholder Engagement Assessment Matrix

Just-in-time (JIT) manufacturing, Kaizen, total productive maintenance
(TPM) , lean management are trends and practices in which knowledge area
of project management? Correct Ans ➡ resource management

Which of the below is correct about the cost baseline? Correct Ans ➡ It is
an output of the Determine Budget process and includes the contingency
reserve

In which of the following organizational structure types is the project
manager's authority weakest? Correct Ans ➡ Functional

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Studycafe. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for CA$27.92. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

72349 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy study notes for 14 years now

Start selling
CA$27.92
  • (0)
  Add to cart