MIS Chapter 14 Study Guide Test. 1) On average, private sector IT projects underestimated budget and delivery time of systems by ________ percent. A) 30 B) 40 C) 50 D) 60 E) 70 - CORRECT ANSWER C) 50 2) As discussed in the chapter, which of the following is not one of the immediate conse...