If a Balancing Authority does not comply with the Control Performance Standard, the Balancing Authority is not permitted to provide which of the following for any other Balancing Authority entities? Regulation of other services related to control performance 1. It is the obligation of each Ba...

[Show more]

Preview 4 out of 60  pages

  • October 13, 2023
  • 60
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
  • NERC
  • NERC
avatar-seller
NERC SOS quiz Questions and Answers
(Already GRADED A)
If a Balancing Authority does not comply with the Control Performance Standard, the Balancing
Authority is not permitted to provide which of the following for any other Balancing Authority entities?

Regulation of other services related to control performance




1. It is the obligation of each Balancing Authority to fulfill its commitment to the Interconnection and not
________ the other balancing Authorities in the Interconnection

Burden




A Balancing Authority is performing Overlap Regulation Service for another Balancing Authority. Which
of the following statements applies to the Balancing Authority providing this service?

The Balancing Authority's Frequency Bias Setting shall be modified to reflect the combined Frequency
Bias Setting of both Balancing Areas.




Balancing Authority A is currently reading a system frequency of 59.95 Hz. Its Net Actual Interchange is
+100 MW and its Net Scheduled Interchange is +200 MW. If Balancing Authority A's frequency bias
setting is 100 MW/0.1 Hz, Balancing Authority A's AGC is pulsing its generators to do what?

Increase MW output




Which of the following is a Real-time measurement of a Balancing Authority's control performance

BAAL




Each Balancing Authority shall monitor which of the following against two standards: CPS1 and BAAL?

,Control performance




In the calculating of CPS1, which of the below conditions would contribute to ta favorable score?

Negative ACE when frequency is high,



positive ACE when frequency is low.




If the frequency bias setting is a higher value than the frequency response of a Balancing Authority and a
frequency decline is caused by a sudden loss of generation is an external balancing area, what will be
the result?

A- The ACE will be a negative value and AGC will increase generation




Which statement best describes the CPS1 requirement?

The Responsible Entity shall operate such that its CPS1 is greater than or equal to 100% for the
preceding 12 month period.




To be in compliance with the BAL-001 requirements, a Balancing Authority must have which of the
following?

CPS1 greater than or equal to 100% and ACE does not exceed the BAAL more than 30 consecutive
minutes




Actual System Frequency (FA) is 60.03 Hz, a Balancing Authority is under-generating slightly to prepare
for an upcoming interchange transaction. What is the Balancing Authority doing?

The BA is helping the Interconnection Frequency.

,You are a Balancing Authority Operator. A neighboring Balancing Authority in the Interconnection
suddenly had a 500 MW generator to trip off line by generator differential. What part of the ACE
equation,

ACE = (NIA-NIS) - 10B (FA-FS) - IME, allows you and other Balancing Authorities in the Interconnection to
contribute to the stabilization of the Interconnection frequency error?

10B (FA-FS)




In your Interconnection, a generator tripped that was large enough to reduce the frequency from 60.000
Hz to 59.940 Hz. Your Balancing Authority's Frequency Bias is 200 MW/0.1 Hz. How many MW would
your system initially contribute to frequency support?

120 MW




Which of the following would be a use of the IME portion of the ACE equation?

Represent flow of a tie line with an out of service meter.




What happens to the Balancing Authority ACE Limit (BAAL) when frequency moves farther away from
scheduled frequency?

The limit gets more restrictive.




How is the Frequency Response Obligation (FRO) of a Frequency Response Sharing Group determined?

By adding the individual FRO's of each member.




A Balancing Authority has an ACE reading of -100MWs and frequency is 60.12 Hz. Is the BA exceeding
the BAAL?

No

, A Balancing Authority that is a member of a Generation Reserve Sharing Group is the Responsible Entity
only in periods during which the Balancing Authority is not in active status under the applicable
agreement or the governing rules for the Generation Reserve Sharing Group.

False




The minimum compliance for NERC DCS is

100% for all reportable disturbances.




A generator tripped in your Interconnection that was large enough to cause frequency to drop to 59.950
Hz. Your Balancing Authority's Frequency Bias is 120 MW/0.1 Hz. How many MWs would your system
initially contribute to frequency support?

60 MWs




A Balancing Authority has a normal load of around 8500 MW. Its most severe single contingency is a
700-MW coal-fired steam unit. At 0810 the ACE value was at -55 MW when a 600-MW generator in the
Balancing Authority's northern area tripped off line as the result of a generator differential. This resulted
in a large negative ACE for the Balancing Authority. What value must the ACE return to and in what time
frame to avoid a DCS violation?

-55 MW ACE in 15 minutes




How is the Frequency Response Measure (FRM) of a Balancing Authority determined?

It is the median of the BA's frequency response for the frequency deviation events identified by NERC
for the previous year.




The Contingency Reserve Restoration period is ________.

ninety minutes

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller ProfGoodlucK. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for £7.95. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

64670 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy revision notes and other study material for 15 years now

Start selling

Recently viewed by you


£7.95
  • (0)
Add to cart
Added