Project Management, 2e (Pinto)
Chapter 12 Resource Management
12.1 True/False
1) There is, for almost all projects, usually a dominant constraint that serves as the final arbiter of
project decisions.
Answer: TRUE
Diff: 1
Section: 12.1 The Basics of Resource Constraints
Skill: Definition
AACSB Tag: Reflective
2) In a resource constrained project, the work must be finished by a certain time, or date, as
efficiently as possible.
Answer: FALSE
Diff: 1
Section: 12.1 The Basics of Resource Constraints
Skill: Definition
AACSB Tag: Reflective
3) All that is needed to create a resource loading calendar is the work breakdown structure and
the activity network.
Answer: FALSE
Diff: 2
Section: 12.2 Resource Loading
Skill: Factual
AACSB Tag: Reflective
4) Because resource management is typically a multivariate, combinatorial problem (i.e., on that
is characterized by multiple solutions involving literally dozens, hundreds, or even thousands of
activity variables) truly correct answers are not possible.
Answer: FALSE
Diff: 2
Section: 12.3 Resource Leveling
Skill: Definition
AACSB Tag: Reflective
5) A resource loading table is created through identifying the project activities and their resources
required to completion and applying this information to the project schedule baseline.
Answer: TRUE
Diff: 2
Section: 12.3 Resource Leveling
Skill: Factual
AACSB Tag: Reflective
, 6) If resources have been over-allocated, the loading table must be reconfigured to eliminate
resource contention points. The project manager can focus solely on the original point of
contention since the activities in a project are separate entities.
Answer: FALSE
Diff: 2
Section: 12.3 Resource Leveling
Skill: Conceptual
AACSB Tag: Reflective
7) Resource loading charts are used to display the amount of resources required as a function of
time on a graph.
Answer: TRUE
Diff: 2
Section: 12.4 Resource Loading Charts
Skill: Definition
AACSB Tag: Reflective
8) If an activity can be split, only the functional portion of the original activity needs to be
accomplished for the project to be fully completed.
Answer: FALSE
Diff: 2
Section: 12.4 Resource Loading Charts
Skill: Factual
AACSB Tag: Reflective
9) The problem of resource underutilization that a project manager faces when managing a single
project disappears in the multi-project environment.
Answer: FALSE
Diff: 2
Section: 12.5 Managing Resources in Multiproject Environments
Skill: Factual
AACSB Tag: Reflective
10) In-process inventory represents the amount of work waiting to be completed but delayed due
to unavailable resources.
Answer: TRUE
Diff: 2
Section: 12.5 Managing Resources in Multiproject Environments
Skill: Factual
AACSB Tag: Reflective
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller smith2324. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for £2.98. You're not tied to anything after your purchase.