The project manager and team should consider each process along with its inputs, tools and outputs. As a result, they should choose which are applicable. This effort is known as - ...
exam questions with accurate answers rated a 100 verified
the project manager and team should consider each process along with its inputs
Written for
CAPM
All documents for this subject (224)
Seller
Follow
QuickPass
Reviews received
Content preview
Certified Associate in Project
Management (CAPM), Exam Questions
with accurate answers. Rated A+./ 100%
verified.
The project manager and team should consider each process along with its inputs, tools and outputs. As
a result, they should choose which are applicable. This effort is known as - ✔✔Tailoring
In Initiating, a project charter is created. According to the PMBOK, which person or group may help
write the charter? - ✔✔Project management team
The Monitoring and Controlling Process Group involves: - ✔✔Tracking, reviewing, and orchestrating the
progress of the project
Much information is collected and distributed during the life of the project. Data that is collected form
controlling processes and analyzed in context is called: - ✔✔Work performance information
The project manager should perform the Initiating processes at the start of each phase in order to: -
✔✔Keep the project focused on the business need
As Planning occurs, more and more is known about the project and the project management plan
becomes increasingly detailed. This detailing is known specifically as: - ✔✔Progressive elaboration
The process group that involves coordinating people and resources, managing stakeholder expectations
and completing the work defined in the project management plan is known as: - ✔✔Executing
The Process group that contains more than 50% of the processes is known as: - ✔✔Planning
, >Direct and Manage Project Work is the process of leading and performing the work defined in the
project management plan. There are several outputs from this process. The only one defined as typically
tangible components completed to meet the project objectives is: - ✔✔Deliverables
In conjunction with the project manager, which person or group needs to address every process and the
project environment to determine the level of implementation for each process? - ✔✔Project team
The key benefit of one of the Integration processes is that it allows stakeholders to understand the
current state of the project, the steps taken, budget, schedule, and scope forecasts. This process is
known as: - ✔✔Monitor and Control Project Work
The project manager should participate in the development of the project charter to better understand
the project requirements. Understanding these requirements will better allow for: - ✔✔Efficient
resource allocation to project activities
As a change control expert, you are asked to work on a plan that documents how changes will be
controlled and monitored on the project. Additionally you are told it will ultimately become part of the
project management plan. This document is known as a: - ✔✔Change management plan
Direct and Manage Project Work requires review of all project changes and the implementation of
approved changes. This may lead to corrective action which is defined as: - ✔✔An intentional activity
that realigns the performance of the project work with the project management plan
As a project team member, you know that the change control board approves or rejects all changes.
During a team meeting, you ask the project manager whose responsibility it is to schedule and
implement the changes. She tells you it is the responsibility of: - ✔✔Project team
On reading the PMBOK, you are uncertain about how the Monitor and Control Project Work Process fits
into the project. On discussion with the project manager, he explains to you that: - ✔✔This process is a
background process and is performed throughout the project
The project manager has held a meeting to describe what documents will be needed to help define the
scope baseline. A major document is the WBS. As a member of the project team with expertise in the
project area, your primary role will be to assist in: - ✔✔Determining the final decomposition of the
project scope into discrete work packages
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller QuickPass. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for £5.12. You're not tied to anything after your purchase.