QUESTION 1
An element of the project scope statement is:
A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget,
D. High-level risks.
Correct Answer: A
QUESTION 2
Which document describes the necessary information to determine if a project is
worth therequired investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case
Correct Answer: D
QUESTION 3
Which input to the Plan Risk Management process provides information on high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets
,Correct Answer: A
QUESTION 4
Which item is an example of personnel assessment?
A. Resource calendar
B. Tight matrix
C. Team-building activity
D. Focus group
Correct Answer: D
QUESTION 5
Which input to the Manage Stakeholder Engagement process provides guidance on
howstakeholders can best be involved in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan
,Correct Answer: D
QUESTION 6
Which input to the Identify Stakeholders process provides information about internal or
external parties related to the project?
A. Procurement documents
B. Communications plan
C. Project charter
D. Stakeholder register
Correct Answer: C
QUESTION 7
The Identify Stakeholders process is found in which Process Group?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Executing
Correct Answer: A
QUESTION 8
An input to Develop Project Charter is a/an:
A. Business case.
B. Activity list.
C. Project management plan.
D. Cost forecast.
Correct Answer: A
QUESTION 9
, Which Knowledge Area involves identifying the people, groups, or organizations that may be
impacted by or impact a project?
A. Project Risk Management
B. Project Human Resource Management
C. Project Scope Management
D. Project Stakeholder Management
Correct Answer: D
QUESTION 10
Which input to Collect Requirements is used to identify stakeholders who can provide
informationon requirements?
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller studyexpertmary. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for £10.96. You're not tied to anything after your purchase.