Typical elements of the project charter include all of the following except - Answer A Project objectives B Project purpose C The project manager's responsibility and authority *D The resources required Which process is the most dependent on the nature of the work being performed? It is th...

[Show more]

Preview 2 out of 9  pages

  • November 30, 2023
  • 9
  • 2023/2024
  • Exam (elaborations)
  • Questions & answers
avatar-seller
PMP Prep Exams
Typical elements of the project charter include all of the following except - Answer A
Project objectives
B Project purpose
C The project manager's responsibility and authority
*D The resources required

Which process is the most dependent on the nature of the work being performed? It is
the process where the deliverables are created. - Answer A Create WBS
B Define Scope
*C Direct and Manage Project Execution
D Monitor and Control Project Work

Which is not part of the Control Scope process? - Answer A Making sure scope creep
does not occur on the project
B Managing project and product scope changes
C Making sure all requested preventive and corrective actions for project scope go
through the Perform Integrated Change Control process
*D Obtaining customer validation on the final deliverable

What are the five project management process groups? - Answer A Planning, concept,
communicating, administration, closeout
* B Monitoring and controlling, planning, executing, closing, initiating
C Inputs, outputs, controls, execution, planning
D Scope, schedule, cost, quality, risk response

You have three projects to choose from: Project A with Internal Rate of Return (IRR) of
20%, Project B with an IRR of 15%, and Project C with an IRR of 17%. Which one
would you choose? - Answer * A Project A
B Project B
C Project C
D None of the above

Project closure includes all of the following except - Answer A Archiving project records
B Conducting lessons learned
*C Verifying product scope
D Conducting a project audit

What documents the project deliverables, acceptance criteria, assumptions, and
constraints? - Answer A The contract statement of work
B Requirements documentation
C Project charter
* D Project scope statement

, Two projects are approximately equal in size. Project A takes four years to complete
and has Net Present Value of $200,000; and project B takes three years to complete
and has NPV of $300,000. Which project should you select? - Answer A Project A
*B Project B
C Project A if it can be reduced to three years
D Project B if it can reduced to NPV of $200,000

There are a number of creative group techniques that can be used to identify product
and project requirements. Which one takes a large number of ideas and groups them
for review and analysis? - Answer A Delphi technique
* B Affinity diagram
C Nominal group technique
D Mind mapping

There are a number of creative group techniques that can be used to identify product
and project requirements. Which one uses a voting process to prioritize ideas generated
in the brainstorming process? - Answer A Delphi technique
B Affinity diagram
*C Nominal group technique
D Mind mapping

The inputs to the Develop Project Plan process include - Answer A Outputs from
planning processes, historical information, organizational policies, constraints, and
assumptions
B Outputs from planning processes, expert judgment, organizational policies, and
Enterprise Environmental Factors
*C Outputs from planning processes, project charter, Organizational Process Assets
and Enterprise Environmental Factors
D Outputs from planning processes, expert judgment, organizational policies,
constraints, and assumptions

PMI® defines a project as having two distinctive characteristics. They are - Answer A
Program and project
* B Temporary and unique
C Product and project
D Cost and schedule

Select the statement that best completes the following statement: If the product scope
description is progressively elaborated, it - Answer * A Has less detail in early phases
and more detail in later phases of the project
B Has no documented detail in early phases of the project
C Requires more detail in early phases of the project
D Contains project requirements

When preparing the project charter, the author should include - Answer *A The business
need the project was undertaken to address

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller THEEXCELLENCELIBRARY. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for £9.58. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

85443 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy revision notes and other study material for 14 years now

Start selling
£9.58
  • (0)
  Add to cart