CPESC Section 1 & 2
What does the acronym NPDES stand for? - CORRECT ANSWER-National
Pollutant Discharge Elimination System
True / False: The NPDES requirements apply only to discharges of storm-water
either directly or through a municipal separate storm drain system, to waters of
the US. - CORRECT ANSWER-2.1.1.6
True
What does the acronym TMDL stand for? Define it? - CORRECT
ANSWER-2.1.1.10
Total Maximum Daily Load. The amount of a particular pollutant that a water body
can assimilate on a daily basis without violating applicable water quality
standards.
Define TMDL - CORRECT ANSWER-2.1.1.10
The TMDL defines the amount of a particular pollutant that a water body can
assimilate on a daily basis without violating applicable water quality standards.
(Water quality standards usually predetermined by the state.)
What are the two types of storm-water permits issued under the NPDES
Program? - CORRECT ANSWER-2.2.1
1. The Construction General Permit (CGP).
2. The individual permit designed to fit the specific requirements of a particular
applicant, facility, or activity.
If deficiencies are found during a SWPPP inspection, how quickly do they need
to be corrected? - CORRECT ANSWER-No later than seven days after the
inspection.
List three types of pollutants. - CORRECT ANSWER-2.1
Nutrients,pathogens, heavy metals, toxics, sediment, salts, detergents,
hydro-carbons,oxygen absorbing substances.
List three examples of 'Waters of the United States'. - CORRECT
ANSWER-2.1.1.6
When does the SWPPP need to be completed? - CORRECT ANSWER-2.3.6.4
Prior to submitting the NOI.
When does the EPA's construction permit require inspections? - CORRECT
ANSWER-Every 7 days, or within 24 hrs of a storm of 0.5 inches or move in
depth.
What does CPESC stand for? - CORRECT ANSWER-Certified Professional in
Erosion & Sediment Control
What are the two types of Storm Water Permits? - CORRECT ANSWER-2.2.1
1. General: provides umbrella coverage to a large number of applicants.
2. Individual: designed to fit the specific requirements of a particular applicant,
facility, or activity.
True/False: A site initially disturbing 1/2 acre, that is part of a 3.5 acre future
development is not required to obtain a permit for the 1/2 acre. - CORRECT
ANSWER-2.1.1.8
False, If it as part of a larger plan of development >1 acre, a permit is required.
Name 3 of the 5 types of Phase I facilities under section 402 of the CWA as of
1987. - CORRECT ANSWER-2.1.1.2
-Facilities already covered by a permit
-Facilities that engage in industrial activity
-Large (>250K pop) MS4s
-Medium (100K250K) MS4s
-Facilities that EPA admin deems "significant contributors" of pollutants to
WOTUS
Who is responsible for applying for the Storm water permit for a construction
site? - CORRECT ANSWER-2.3.1
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller modocko752. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for £6.51. You're not tied to anything after your purchase.