The MOST specific information about the size and location of windows would be found in a
Floor plan
What direction does heat flow?
Hot to cold
What are batter boards
stakes and ledger boards marking building lines
What is the MAXIMUM distance between a ventilating opening in an under-floor space and each
corner of the building?
3 feet
What is NOT required in exterior nonbearing walls?
Load-bearing headers
A lengthwise grain separation between or through the growth rings of lumber is called a
Shake (c 326)
The abbreviation "d" in "16d" means
Penny
Notches may not be located in the ____________ of a joist span
Middle 1/3
How should board and batten be installed?
1 inch overlap 10d nails
What is the maximum allowable notch in ceiling joists
1/6 the depth of the member
How MUST rafters be framed to each other
Gusset plate (R802.3)
What is used to prevent buckling at points of high stress?
Squash blocks
Prior to the installation of wood floor how long for acclimation?
, 4-5 days
Where do you start laying parquet flooring
Centerline
What is the first step in carpet installation?
Tackless strip
What type of nail is used in floor installation
7d or 8d threaded/Cut steel
What should be applied to crevices in wood flooring?
Filling
What is the best nail for hardwood
Ring shank nail
What is the maximum size of a floor frame opening?
5 sq ft (62) (R310.2.1)/ 4 ft header joist (130) (R502.10)
When installing a string of wall cabinets, the cabinets should
Be attached to the adjacent cabinets before to the wall
What is the MINIMUM height for a stairway handrail
34 inches
A third stairway stringer should be used when the stair width exceeds
30 inches
What type of nail are best for general construction?
Smooth shank
What is the MAXIMUM flame spread index for insulation materials
25 (R302.10.1)
What is the MAXIMUM dimension of the ventilation coverings for under-floor space
1/4 inch (R 408.2)
Flexible insulation placed in floor joists above an unheated crawl space should
Be well supported between joists/using a wire mesh or rigid board (c 904-5)
In a crawl space how far from the floor joints do you need to place vapor retarder
Top Soil
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller ACADEMICAIDSTORE. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for £8.78. You're not tied to anything after your purchase.