A fill line in an oil burner system is a line used to: - Answer - Fill the storage tank with oil.
The aquastat is located - Answer - Below the water line.
All heating, combustion, and cooking equipment shall be installed with adequate clearances from
_______ construction. - Answer - Combustible
The equipment must be provided with ______ or the building construction shall be _____ _____. -
Answer - Insulation.
Fire Protected
During operation the surface of combustible construction materials will not be raised to a temp higher
than _____ degrees F. - Answer - 170 degrees
Equipment shall be so that the means of access for ordinary operation and maintenance will not be
_______. - Answer - Hazardous
Acceptance Tests:
Boilers shall not be placed in operation until they have been _____ and ____ and an equipment ____
_____ has been issued by the ______. - Answer - Inspected and tested.
Use permit, commissioner
Periodic Inspections: All boilers must be inspected at least _____ a _____ including chimney
connections. - Answer - Once a year
Owners Annual Statement: The owner of each boiler shall file an _____ written statement with the
________, specifying the _____of each boiler and ______ for inspection. - Answer - Annual,
commissioner, location, arrangement.
Field Tests: all piping and oil storage tanks shall be _______ tested for tightness by the ______ before
the system is operated. - Answer - Hydrostatically, contractor
, The piping shall be tested at _____ times the max working pressure applicable to that part of the piping
system but at a pressure ____ than the test pressure required for the storage tank. - Answer - 1/2, less
The min pressure for testing tanks shall be ____ times the max working pressure but in no case less than
____ psi. - Answer - 1 1/2, 25 psi
The hydrostatic pressure must be maintained until all ____ and _____ have been visually inspected for
___, but in no case less than _____ hour. - Answer - Joints, connections, leaks, 1/2 hour.
A record must be kept of the pressure test showing the name of the _____ and the _____ at which the
piping and tank were tested. - Answer - Contractor, pressure
Gas piping must be tested by the _____ before operation. - Answer - Contractor
For oil burning systems, ____ ____ giving instructions for the care and operation of the system shall be
permanently located in an easily _____ and _____ location near the equipment. - Answer - Instruction
Cards, visible, accessible
No oil burning equipment shall be operated until an equipment ____ _____ has been issued by the
commissioner, the requirements of the ____ ____ control code have been met and until the approval
for the storage of ____ ____ has been given by the fire commissioner. - Answer - Use permit, air
pollution, fuel oil
Every oil burning installation that is not fully automatic or requires preheating shall be operated under
the direct supervision of a person holding a ____ ___ ______ issued by the FD. - Answer - COF
Such person must be in the building at ____ ____ while in operation and present in the _____ _____
during startup. - Answer - All times, boiler room
After any repairs to the boiler are made, ______ shall check the repairs and the functioning of all ____
_____ and the positioning of the ______. - Answer - Operators, control devices, valves
All heating and combustion equipment that is fired with solid, liquid, or gas fuels, must comply with the
requirements of the ____ _____ _____ code. - Answer - Air pollution control
Low Temp Equipment have a temp of ____ degrees at the point of leaving the equipment. - Answer -
600 or less
Median Temp Equipment have a temp of between ___ and ___ degrees F at the point of leaving the
equipment under normal conditions. - Answer - 600 and 1000
High Temp Equipment have a temp of ____ or ____ degrees F leaving the equipment. - Answer - 1000
or greater
Ventilation shall be capable of providing at least ____ cfm of air for each gallon of oil per ____. - Answer
- 36, hour
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Wisdoms. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for £8.19. You're not tied to anything after your purchase.