100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
ACG CxA Exam (CH 4: Cx Team) – Questions and Answers £6.89   Add to cart

Exam (elaborations)

ACG CxA Exam (CH 4: Cx Team) – Questions and Answers

 1 view  0 purchase

ACG CxA Exam (CH 4: Cx Team) – Questions and Answers

Preview 2 out of 5  pages

  • September 7, 2024
  • 5
  • 2024/2025
  • Exam (elaborations)
  • Questions & answers
All documents for this subject (1)
avatar-seller
Victorious23
ACG CxA Exam (CH 4: Cx Team) – Questions and Answers

Identify typical team member of the Cx Team. - -1. Owner
2. End user
3. architect
4. electrical engineer
5. mechanical engineer
6. commissioning authority
7. controls contractor
8. mechanical contractor
9. electrical contractor
10. sheet metal contractor
11. TAB agency
12. General or construction manager
13. owners O&M staff

-Comprehensive Commissioning - -1. commissioning starts at the inception
of a building project during the pre-design phase, and continues through the
post-acceptance phase.
2. provides an opportunity to cultivate a quality management focus among
all design and construction team members as they become involved with the
project

-Which Chapter of the ACG guideline identifies detailed methodology for
Comprehensive HVAC Commissioning? - -Chapter 5

-What are the Comprehensive Commissioning phases? - -Pre-design
Design
Construction
Acceptance
Post Acceptance

-Comprehensive Commissioning: Pre-design phase - -1. Commissioning
established as integral part of project
2. The owner selects the commissioning authority
3. Develop the scope of commissioning
4. Commissioning authority reviews design intent document

-Comprehensive Commissioning Design phase - -1. Review design to ensure
it accommodates commissioning
2. Write commissioning specifications defining contractor
responsibilities
3. Commissioning authority writes the commissioning plan
4. Establish the project schedule

, -Comprehensive Commissioning Construction phase - -1. Commissioning
authority reviews contractor submittals
2. Commissioning authority updates commissioning plan
3. Commissioning process is coordinated—through project
schedule, commissioning plan and commissioning plan
and commissioning meetings
4. Carry out and document system verification checks
5. Carry out the document equipment and system start-ups
6. TAB agency completes and documents TAB work

-Comprehensive Commissioning Acceptance phase - -1. Carry out FPTs on
all HVAC systems
2. Train the O&M staff for effective, ongoing operations and maintenance of
all systems
3. Provide full documentation

-Comprehensive Commissioning Post-Acceptance phase - -1. Correct any
deficiencies, carry out required re-testing
2. Carry out any required "off-season" tests
3. Update documentation as required

-Identify the Comprehensive HVAC commissioning organizational structure
for Plan & Spec - -

-During commissioning what statements identify the CxA's role? - -1.
Authority leads the commissioning process, and works
cooperatively with the designers and contractors, but always in the owner's
interest
2. Facilitates communication and coordination among designers, contractors
and suppliers.

-Identify the Comprehensive HVAC commissioning organizational structure
for Design Build - -

-If the project uses the traditional plan and spec process, the commissioning
authority will typically report directly to who? - -The Owner

-Define Construction HVAC Commissioning—New Construction. - -Takes
place during the construction,
acceptance and post-acceptance phases of the project.

-Which Chapter of the ACG guideline identifies detailed methodology for
Contruction HVAC Commissioning? - -Chapter 6

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller Victorious23. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for £6.89. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

81989 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy revision notes and other study material for 14 years now

Start selling
£6.89
  • (0)
  Add to cart