FAM 104 Test 1 Questions with All Correct Answers
Define Project Management - Answer- a discipline, a set method, theories and techniques that have evolved to manage the complexities of work that is unique & temporary
5 project success factors - Answer- 1) Agreement of a product team, custom...
Define Project Management - Answer- a discipline, a set method, theories and
techniques that have evolved to manage the complexities of work that is unique &
temporary
5 project success factors - Answer- 1) Agreement of a product team, customer and
management of the goals
2) A plan showing overall path and a clear responsibility which can be used to measure
progress
3) Constant, effective communication among everyone involved
4) Controlled Scope
5) management Support
Project vs On-going operation - Answer- Project - work that is done on time, has a
beginning and end. Produces unique product
On-going Operations - no end point specified. Producing similar often identical products
Identify 3 overarching skill areas in which a project manager must be knowledgable -
Answer- 1) Project Management
2) Business Management
3) Technical Skills
Define Project Success - Answer- Cost, Schedule and Performance
Office Functional Disciplines - Answer- System EN, CO, PM, FM, LG, Test
Define Work Breakdown Structure - Answer- A tool used to break a project down into
manageable pieces of work. Deliverable oriented
Steps:
1) what are your major deliverables
2) identify all tasks required
3) Organize the WBS
, Explain how a WBS clarifies and provides necessary details for project management
activities - Answer- Helps to:
- provide a detailed illustration of project scope
- Monitor progress
- Helps provide accurate cost and schedule (not a schedule, helps build one)
- Build your project team
- serves as the foundation for your project plan
Summary Task vs Work Package - Answer- Summary Tasks has branches underneath.
(no work)
Work Packages have work associated with them
Explain the considerations in determining how far to extend a WBS branch - Answer-
3rd or 4th level (don't do contractors work)
8/80 rule
Importance of Critical Path and Slack/Float - Answer- Critical Path - Events that directly
affect the schedule. (have zero slack)
Slack - can slip without affecting the schedule.
Identify the planning steps involved with developing a project schedule - Answer- 1)
Build a WBS - identify activities and develop the precedence relationships associated
2) Identify task relationships - construct a diagram
3) Estimate activity durations
- Parametric - find some parameter that relates to schedule
- Expert opinion
- Analogy - find a similar system and relate
4) Calculate initial schedule via CPM
5) Assign and Level Resources
Critical Path Method - Answer-
Program Evaluation and Review Technique (PERT) vs Monte Carlo - Answer- PERT -
Only looks at Critical Path, uses statistics and a normal distribution, More Optimistic
Monte Carlo - Considers all paths through a network, Computer generates random
number for durations, More robust
Identify Ways for balancing a project at the project level - Answer- Triple constraint
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller Scholarsstudyguide. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for £10.16. You're not tied to anything after your purchase.