Final Assignment in Cost Studies M2CPM9

 13 views  0 purchase

Construction of 30 New Two-Storey Detached Houses - Housing Development Project in NG8 Area of Nottingham

Preview 3 out of 22  pages

  • February 13, 2024
  • 22
  • 2022/2023
  • Other
  • Unknown
All documents for this subject (1)
avatar-seller
mwapemwansa2019
Course: MSc. Construction Project Management
Module: Cost Studies
Assignment No.: Final Assignment

Construction of 30 New Two-Storey Detached Houses - A
Housing Development Project in NG8 Area of Nottingham




June 2023

,Contents
1.0 Introduction................................................................................................................................................................... 2

1.1. What is Cost Estimation in Construction? ............................................................................................................ 2

2.0. The Assignment Task .................................................................................................................................................. 2

3.0 Task 1 - Preparation of an Order of Cost Estimate (OCE)...................................................................................... 2

4.0 Task 2 - Preparation of an Elemental Cost Plan (Cost Plan 1) ............................................................................ 10

5.0 Task 3 - Preparation of a Cost Appraisal for Two (2) Roofing Options............................................................... 14

6.0 Task 4 - Determination of Monthly Working Capital Requirements .................................................................... 16

7.0 References: .................................................................................................................................................................. 20

, 1.0 Introduction
1.1. What is Cost Estimation in Construction?
Cost Estimation in construction is a technique used to comprehensively calculate costs in order to
determine the total budget needs for the completion of a project. Like any other phase of a project,
preconstruction cost estimates directly affect the intended goals. In cost estimation each element
required on the project is considered. Among the many benefits of cost estimation, some of the
most significant are easy budget planning, resource allocation, effective risk management and
improved decision making. Estimating costs on a project is characterized by predicting quantity, cost
and price of the resources needed based on the project scope.

2.0. The Assignment Task
We have been appointed as Cost Managers for a housing development involving the construction of
thirty (30) new two-Storey detached houses, to be located at the NG8 area of Nottingham believed
to be in high demand. The site is being developed by a local developer and the budget for capital
costs is at £5.9 million.
There are four (4) main tasks that need to be done. These are;
1. Production of an Order of Cost Estimate (OCE) using the data provided.
2. Preparation of an elemental cost plan (Cost Plan 1) as a progression from the Order of Cost
Estimate (OCE).
3. Preparation of a cost appraisal indicating the comparative performance of the two (2) roofing
options over 100 years.
4. Determination of the working capital requirements from month to month.

3.0 Task 1 - Preparation of an Order of Cost Estimate (OCE)
An Order of Cost Estimate (OCE) is a document that helps establish a realistic cost limit for a
building project, its viability and makes the employer aware of any financial commitments prior to
them developing the most preferred option.
In this assignment, there is need to determine the principal area measurements and dimensions
based on the drawings provided. The method adopted is the floor area method. To determine the
principal area measurements, the following procedure is undertaken by calculating the following;

i. Gross Internal Floor Area (GIFA) on the ground floor.
ii. Gross Internal Floor Area (GIFA) on the first floor.
iii. Area of roof structure.
iv. Area covered by the roof.
v. Height of internal walls on the ground floor.
vi. Height of internal walls on the first floor.
vii. Calculating the Net Internal Area (NIA) on the ground floor.
viii. Calculating the Net Internal Area (NIA) on the first floor.

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through credit card for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying these notes from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller mwapemwansa2019. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy these notes for £6.51. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

73216 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy revision notes and other study material for 14 years now

Start selling
£6.51
  • (0)
  Add to cart