on an impressed current cathodic protection system
all are examples of acceptable release detection f
when a steel tank is installed with a galvanic cp
Geschreven voor
UST Inspector Eam
UST Inspector Eam
1
beoordeling
Door: warrenbrannoch • 2 weken geleden
Door: phyliswambui996 • 2 weken geleden
I wish you all the best in your studies and in need of any study material ask and i will gladly help....thanks for the review, I really appreciate your feedback. Welcome again to my page!!
Verkoper
Volgen
phyliswambui996
Ontvangen beoordelingen
Voorbeeld van de inhoud
U3 ICC Tank Tightness Testing
On an impressed current cathodic protection system, the negative wire of the rectifier is
connected to the:
a. Anode
b. Cathode
c. Drop tube
d. Dielectric union
b. Cathode
Brainpower
Read More
Previous
Play
Next
Rewind 10 seconds
Move forward 10 seconds
Unmute
0:00
/
0:00
Full screen
All are examples of acceptable release detection for tanks, except:
a. Impressed current cathodic protection
b. Automatic tank gauging
c. Statistical inventory reconciliation
d. Soil-vapor monitoring
a. Impressed current cathodic protection
When a tank is temporarily closed, the cathodic protection system:
a. Must be turned off
b. Must remain in operation
c. Should be removed
d. Operator can have it on or off.
b. Must remain in operation
, When a steel tank is installed with a galvanic CP system attached, the tank gauges are usually
connected through a riser with a dielectric bushing. What is the purpose of that?
a. To prevent static discharge
b. To minimize effects of noise
c. To electrically isolate the tank from the tank gauge
d. To prevent water intrusion in the tank
c. To electrically isolate the tank from the tank gauge
Factory-installed diectric coatings may include all of the following except:
a . Asphalt
b. epoxies
c. Enamels
d. fiberglass-reinforced plastic
a . Asphalt
According to the EPA, Tank tightness test data must be maintained for:
a. 18 months
b. 3 years
c. 5 years
d. Until the next test is performed
d. Until the next test is performed
How long must records of UST system repairs be available on site?
a. 60 days
b. 1 year
c. 5 years
d. for the remaining lifetime of the UST system
d. for the remaining lifetime of the UST system
In the event of a release, what is the reporting requirement?
a. ICC licensed supervisor must report the leak within 24 hours
b. Owner/Operator must report the leak within 24 hours
c. Owner/Operator must report the leak within 18 hours
d. ICC licensed supervisor must report the leak within 18 hours
b. Owner/Operator must report the leak within 24 hours
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper phyliswambui996. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €10,72. Je zit daarna nergens aan vast.