A firestops ability to provide a smoke stop. (air leakage rate)
To avoid damaging cable jacket, how often must you securely fasten electrical nonmetallic tubing (ENT)
3 Feet so it does not damage the c...
L Rating
A firestops ability to provide a smoke stop. (air leakage rate)
To avoid damaging cable jacket, how often must you securely fasten electrical
nonmetallic tubing (ENT)
3 Feet so it does not damage the cable
What is the minimum dedicated power requirement of a telecommunications
enclosure
120 V ac/20
The clearance behind the PBB when mounted, should be no less than-
2inch clearance behind the PBB when mounted
When installing a plywood backboard, you should use galvanized screws that are
a minimum of ______ longer than the depth of the wall covering, including the
plywood
0.5in
The use of under carpet telecommunications cable should be limited to:
The interconnection point between horizontal cabling and UTC is a transition point (TP)
Two 90-degree bends are allowed in any one conduit segment. A third bend may
be acceptable under certain situations
Runs under 33 feet
When installing racks and cabinets on an access floor, what should they be
secured to?
The frame
When placing cabinets on an access floor, how should the cabinets be aligned?
One edge flush with the floor tile cut line
What is a telecommunications enclosure TE used for?
, May be used to provide a suitable option for moves, adds, and changes without
compromising infection control measures and other restrictions
What size threaded rod would you typically use in a heavy duty ladder rack
installation?
5/8in
A supplemental bonding network within an ER or data center consisting of a set
of conductors formed into a grid is often associated with what?
Access flooring
Which type of anchor requires a hole to be drilled into the floor where the
attachment is to be made?
Expansion anchors
Min seperation from electric motors and transformers?
48"
During which phase of the project would you determine cable labeling
requirements?
Pre-construction Phase
What type of documentation uses the original floor plans and reflects the actual
installed outlet locations, cables, length, and firestopping materials?
Record drawings
Which project document is used to request clarification, supplemental
information, or approval of material substitutions?
RFI
Comparing design documents to existing conditions, verifying parking access,
and determining the work hours are all examples of what you would learn during
A job start
T1
Layout of complete building per floor; serving zone boundaries, backbone distribution
systems, and horizontal pathways
T0
Campus or site plans; exterior pathways and interbuilding systems
T3
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper NurseAdvocate. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €8,84. Je zit daarna nergens aan vast.