1.A person who engages in a business or activity that involves construction new water wells must possess a license from the:: Oregon Water Resource Department (OWRD)
2.True or False
Prompt billing and prompt collections make for a healthier cash flow.: True
3.Oregon OSHA consultants WILL NOT:: Issue citations or propose penalties for violations of OSHA standards .
4.1) Questions to answer when preparing your project schedule include all of these except:
-All of these are questions to ask
-What equipment will be needed?
-How long will each task take to complete?
-What type of crew will be needed to complete the activity?: - All of these are questions to ask
-What equipment will be needed?
-How long will each task take to complete? -What type of crew will be needed to complete the activity?
5.For Notice of Right Lien purpose, a commercial improvement is defined as:: A structure that is not used or intended for use as a residential building
6.I am the residential original contractor and I provide labor and materials for the project. Who do I need to give a notice of Right to Lien to?: Mortgagee
7.A quantity survey is also referred to as a:: Take Off
8.Tagout involves placing a warning tag:: On an energy-isolation device
9.Other than Take Off, other common construction estimate types include all, except:: Ballpark Estimates
10.True or False
An on-site of host employer is responsible for ensuring a safe place of employment for leased or temporary workers.: True
11.The state unemployment tax rate varies base on:: The history of unemploy- ment claims against the employer.
12.Stop work order violations can result in:: - Any of these could be the result of failure to comply with a stop work order .
-Court action -Permit or license revocation
-Civil penalties
13.The gives an overview of the project, deadlines, and general requirements.: Invitation to Bid
14."Job Logic" refers to:: The sequence of work .True or False
Self-employment taxes apply to all forms of business entities.: False
16.- Money earned and money spent are accounted for in the year they are received or paid, respectively.: In the Cash Method
17.The Itemized Summary is the basis for:: A complete and accurate estimate of project costs and lists all major items of work in the order they are to be performed.
18.A major difference between the EIN and the BIN is:: One is federal and one is state
19.Poor construction and storage practices can result in inside the structure walls.: Molds and fungus
20.Builders now must use corrosion-resistance flashing in these specified locations, except:: Surrounding all interior bedroom doors .
21.Compliance with environmental regulations can protect a contractor from:
-All of these are correct
-Private party lawsuits
-Criminal and civil penalties
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper BESTGOODIES. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €12,69. Je zit daarna nergens aan vast.