Clean Water Act - ANS-Law set into place in 1970 for storm water regulation
NPDES - ANS-Regulations for monitoring storm water activity on a construction site, are
outlined in
Immediately after project is awarded and before you begin any site work - ANS-When
should you read and understand SWPP
Contaminated ground water - ANS-What is not an allowable storm water discharge or
non-storm water discharge
When jurisdiction of operations specifies you can start - ANS-When may construction
activity begin
303D list - ANS-Waters that fail anti-degradation list are placed on which list.
An officer and project owner - ANS-SWPPPs certification are signed by who
FALSE - ANS-The document that must be completed signed and submitted to the state
to obtain authorization to discharge is the NOT. (T/F)
All construction has been completed both inside and outside - ANS-NOT can be filed
when
is in charge of daily activities - ANS-Operations on a construction site are the entity in
charge of plans and specification and the entity who?
Stay out of trouble with the law - ANS-Motives for staying in compliance with storm
water objectives?
To protect and preserve beneficial use of U.S. waters, maintaining their clean, physical
and biological integrity - ANS-Objectives of the clean water act are
National Pollutant Discharge Elimination System - ANS-NPDES stands for
, Site description and maps, inspection and maintenance procedure. Potential pollutant
sources, schedules of activities, site contact information, plan certification documents,
site contact info and descriptions of controls BMP - ANS-Which are a component of a
good SWPPP
False - ANS-Construction sediment is not considered a potential pollutant source (T/F)
Project owner, SWPPP designer - ANS-When modifying or substituting a storm water
BMP the contractor must consult with
False - ANS-NOI must be submitted to the appropriate agency before the storm water
pollution preventive plan is developed (T/F)
False, 303d List - ANS-Name of the list with impaired waters is called totally daily
maximum load (T/F)
It is required by law, it documents storm water management activity on your site, and it
demonstrates your intent to manage storm water on your site - ANS-You should have a
SWPPP for your construction site because?
Site specific - ANS-A well constructed SWPPP for your site should be?
Prior to commencing construction - ANS-The NOI must be submitted when?
Schedule of activities - ANS-One necessary component of a good SWPPP is?
Weather and Climate - ANS-Factors that may impact SWPPP scheduling activities
include
masonry materials, petroleum storage tanks, soil amendments fertilizer, lime etc -
ANS-Pollutant sources on a construction may include
Seek written approval of the project SWPPP designer or project owner - ANS-If you
believe BMP modification are necessary to the site you must?
Endangered species and historical preservation - ANS-The following consideration may
be incorporated into the SWPPP?
Site maps, erosion sediment control, BMPs, site specific sequences of construction
activities - ANS-The SWPPP will contain the following?
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper EXAMQA. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €11,37. Je zit daarna nergens aan vast.