CDT Exam Questions and Answers
(Latest Update 2024)
Which of these documents, might we find in the
Project Manual but they are not contract documents?
(A) The Agreement
(B) Procurement Documents
(C) Addendum
(D) Supplemental Conditions - Correct Answer ✅Answer:
B
Reference: PDPG 11.1.6
Explanation: Procurement requirements are
addressed to prospective bidders or proposers
interested in the project. Although not necessarily
part of a contract, the procurement requirements are
usually bound with other written construction
documents into a project manual.
,CDT Exam Questions and Answers
(Latest Update 2024)
Before a model building code can become the
building code for a jurisdiction, it has to be adopted
by?
(A) Authority Having Jurisdiction
(B) State Government
(C) Building Inspector
(D) International Organization for
Standardization - Correct Answer ✅Answer: A
Reference: PDPG 4.3
Explanation: Before a model building code can
become the building code for a jurisdiction, it has to
be adopted by that AHJ. Once adopted, they then
are responsible for enforcing that building code
within their jurisdiction.
,CDT Exam Questions and Answers
(Latest Update 2024)
The Construction Manager is hired by this entity?
(A) The General contractor
(B) Owner
(C) A/E
(D) Contract Administrator - Correct Answer ✅Answer: B
Reference: PDPG 2.6.4
Explanation: The owner usually engages the
services of a construction manager, an entity that
typically contracts with the owner to provide
construction management services.
The parties to the Construction Agreement are?
(A) General Contractor, Sub Contractor, and
Construction Manager
, CDT Exam Questions and Answers
(Latest Update 2024)
(B) A/E, General Contractor, and Contract
Administrator
(C) Building Official, and General contractor
(D) Owner, Contractor, and A/E - Correct Answer
✅Answer: D
Reference: PDPG 7.2.3.1
Explanation: (PDPG Figure 5.1) The tripartite relationship
among the owner, contractor,
and A/E is created by obligations to third parties to the
contract. For example, the
owner-A/E agreement may require certain duties of the
A/E acting on behalf of the owner
during construction. The contractor has a right to rely on
the proper performance of these
duties. The A/E, similarly, relies on the contractor to
perform certain duties identified in
Voordelen van het kopen van samenvattingen bij Stuvia op een rij:
Verzekerd van kwaliteit door reviews
Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!
Snel en makkelijk kopen
Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.
Focus op de essentie
Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!
Veelgestelde vragen
Wat krijg ik als ik dit document koop?
Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.
Tevredenheidsgarantie: hoe werkt dat?
Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.
Van wie koop ik deze samenvatting?
Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper Allivia. Stuvia faciliteert de betaling aan de verkoper.
Zit ik meteen vast aan een abonnement?
Nee, je koopt alleen deze samenvatting voor €12,19. Je zit daarna nergens aan vast.