Test Bank for Project Management A Socio-Technical Approach 2024 Release By Erik Larson, Clifford Gray and Pinyarat Sirisomboonsuk €17,20   In winkelwagen

Tentamen (uitwerkingen)

Test Bank for Project Management A Socio-Technical Approach 2024 Release By Erik Larson, Clifford Gray and Pinyarat Sirisomboonsuk

1 beoordeling
 112 keer bekeken  5 keer verkocht
  • Vak
  • Tests Bank
  • Instelling
  • Tests Bank
  • Boek

Test Bank for Project Management A Socio-Technical Approach 2024 Release By Erik Larson, Clifford Gray and Pinyarat Sirisomboonsuk

Voorbeeld 4 van de 534  pagina's

  • 31 augustus 2024
  • 534
  • 2024/2025
  • Tentamen (uitwerkingen)
  • Vragen en antwoorden
  • Tests Bank
  • Tests Bank

1  beoordeling

review-writer-avatar

Door: adolfogarza79 • 1 maand geleden

avatar-seller
Test Bank for
Project Management A Socio-Technical Approach 2024 Release By Erik Larson,
Clifford Gray and Pinyarat Sirisomboonsuk
Chapter 1-16 Answers are at the End of Each Chapter

Chapter 1
Student name:
1) Which of the following choices is a professional organization for project managers?

A) PMI.
B) AMA.
C) MIS.
D) IPM.
E) PMBOK.




2) Which of the choices listed below is NOT considered to be a characteristic of a project?

A) An established objective
B) A clear beginning and end
C) Specific time, cost and performance requirements
D) For internal use only
E) Something never been done by a particular company before




3) Which of the choices listed below is NOT considered a project?

A) Developing a new software program
B) Designing a space station
C) Preparing the site for the Olympic Games
D) Production of automobile tires
E) Developing a new advertising program




4) Which of the following activities is the best example of a project?
Version 1 1

, A) Processing insurance claims
B) Producing automobiles
C) Writing a policy manual
D) Monitoring product quality
E) Overseeing customer requests




5) Which of the following is NOT one of the stages of a project life cycle?

A) Identifying
B) Defining
C) Planning
D) Executing
E) Closing




6) In which stage of the project life cycle are project objectives established, teams formed,
and major responsibilities assigned?

A) Identifying
B) Defining
C) Planning
D) Executing
E) Closing




7) In which stage of the project life cycle is a major portion of the actual project work
performed?

A) Identifying
B) Defining
C) Planning
D) Executing
E) Closing



Version 1 2

,8) In which stage of the project life cycle are you more likely to find status reports, changes,
and the creation of forecasts?

A) Identifying
B) Defining
C) Planning
D) Executing
E) Closing




9) In which stage of the project life cycle is the project’s schedule and budget determined?

A) Identifying
B) Defining
C) Planning
D) Executing
E) Closing




10) In which stage of the project life cycle is the product of the project delivered to the
customer and resources are released from the project?

A) Identifying
B) Defining
C) Planning
D) Executing
E) Closing




11) Which of the following is NOT typical of a project manager?




Version 1 3

, A) Managing a temporary activity
B) Overseeing existing operations
C) Managing a nonrepetitive activity
D) Responsible for time, cost and performance trade-offs
E) Work with a group of outsiders, including vendors and suppliers




12) Which of the following is NOT one of the driving forces behind the increasing demand
for project management?

A) Compression of the product life cycle
B) Knowledge explosion
C) Increasing need for concurrent multi-project management
D) Declining need for product customization
E) More sustainable business practices




13) Project management is ideally suited for a business environment requiring all of the
following EXCEPT

A) Accountability.
B) Flexibility.
C) Innovation.
D) Speed.
E) Repeatability.




14) Which dimension of project management centers on creating a temporary social system
within a larger organizational environment that combines the talents of a divergent set of
professionals working to complete the project?




Version 1 4

Voordelen van het kopen van samenvattingen bij Stuvia op een rij:

Verzekerd van kwaliteit door reviews

Verzekerd van kwaliteit door reviews

Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!

Snel en makkelijk kopen

Snel en makkelijk kopen

Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.

Focus op de essentie

Focus op de essentie

Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!

Veelgestelde vragen

Wat krijg ik als ik dit document koop?

Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.

Tevredenheidsgarantie: hoe werkt dat?

Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.

Van wie koop ik deze samenvatting?

Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper solutions. Stuvia faciliteert de betaling aan de verkoper.

Zit ik meteen vast aan een abonnement?

Nee, je koopt alleen deze samenvatting voor €17,20. Je zit daarna nergens aan vast.

Is Stuvia te vertrouwen?

4,6 sterren op Google & Trustpilot (+1000 reviews)

Afgelopen 30 dagen zijn er 73918 samenvattingen verkocht

Opgericht in 2010, al 14 jaar dé plek om samenvattingen te kopen

Start met verkopen
€17,20  5x  verkocht
  • (1)
  Kopen