100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten
logo-home
WMGT 322 Question and answers correctly solved 2024/2025 €16,96
In winkelwagen

Tentamen (uitwerkingen)

WMGT 322 Question and answers correctly solved 2024/2025

 1 keer verkocht
  • Vak
  • WMGT
  • Instelling
  • WMGT

WMGT 322 Question and answers correctly solved 2024/2025 WMGT 322 (From the Initial Stages of Project Development) Which of the following could be considered stakeholders for a Civil Engineer project? Select ALL that apply. - correct answer Contracting Officer Facility User Communications Sq...

[Meer zien]

Voorbeeld 2 van de 7  pagina's

  • 19 september 2024
  • 7
  • 2024/2025
  • Tentamen (uitwerkingen)
  • Vragen en antwoorden
  • WMGT
  • WMGT
avatar-seller
WMGT 322
(From the Initial Stages of Project Development) Which of the following could
be considered stakeholders for a Civil Engineer project? Select ALL that
apply. - correct answer ✔Contracting Officer
Facility User
Communications Squadron Representative
Airfield Manager


(From the Initial Stages of Project Development) Which of the following
documents could be considered part of the project record? Select ALL that
apply. - correct answer ✔Independent Government Estimate
Quality Control Plan
Contractor Submittals


(From the Initial Stages of Project Development) A SABER contractor submits
a project invoice to the government that includes rental of a 25K Forklift. The
construction inspector for this project clearly recalls that the only forklift used
on the jobsite was a smaller 5K forklift, which costs significantly less money to
rent. Which document in the project record could be used to dispute this
claim? - correct answer ✔AF Form 1477 Daily Construction Inspection
Report


(From the Programming Fundamentals Lesson) You are working on a project
and determine a change order is needed because the beams were too small
to handle the roof load. However, this would exceed the approval authority for
this Construction project. What is a viable option for the project team? -
correct answer ✔Resubmit the project to obtain appropriate approval even if
work must stop while the approval is obtained.

, (From the Programming Fundamentals Lesson) If a project modifies an
existing facility to make it compliant with current codes and regulations, it is
likely a(n) _______ project. - correct answer ✔Repair


(From the Programming Fundamentals Lesson) Match the class of cost
estimate with its definition and use (not all options will have a match). - correct
answer ✔Class 1: Unit Price
Used to negotiate and compare bids with Contractors.


Class 3: Parametric Used for budgeting and making the official Programmed
Amount.


Class 5: Square Foot Used for long range planning when the scope is still
poorly defined.


(From the Programming Fundamentals Lesson) Determining the Work
Classification is one of the most important steps in the programming process,
before determining the Fund Source and Program Avenue. Work
Classification can be defined as: - correct answer ✔Describing the nature of
the work to be accomplished


(From the Project Management Plan Lesson) Who is responsible for creating
a Project Management Plan? - correct answer ✔Project Manager


(From the Project Management Plan Lesson) At what phase in the Air Force
project lifecycle should a Project Management Plan be developed? - correct
answer ✔Planning and Programming


(From the Project Management Plan Lesson) MSgt Jones is an extremely
competent SNCO that has years of experience working on high voltage power
projects. You have recently been appointed project manager for a new power

Dit zijn jouw voordelen als je samenvattingen koopt bij Stuvia:

Bewezen kwaliteit door reviews

Bewezen kwaliteit door reviews

Studenten hebben al meer dan 850.000 samenvattingen beoordeeld. Zo weet jij zeker dat je de beste keuze maakt!

In een paar klikken geregeld

In een paar klikken geregeld

Geen gedoe — betaal gewoon eenmalig met iDeal, creditcard of je Stuvia-tegoed en je bent klaar. Geen abonnement nodig.

Direct to-the-point

Direct to-the-point

Studenten maken samenvattingen voor studenten. Dat betekent: actuele inhoud waar jij écht wat aan hebt. Geen overbodige details!

Veelgestelde vragen

Wat krijg ik als ik dit document koop?

Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.

Tevredenheidsgarantie: hoe werkt dat?

Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.

Van wie koop ik deze samenvatting?

Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper flyhigher329. Stuvia faciliteert de betaling aan de verkoper.

Zit ik meteen vast aan een abonnement?

Nee, je koopt alleen deze samenvatting voor €16,96. Je zit daarna nergens aan vast.

Is Stuvia te vertrouwen?

4,6 sterren op Google & Trustpilot (+1000 reviews)

Afgelopen 30 dagen zijn er 64670 samenvattingen verkocht

Opgericht in 2010, al 15 jaar dé plek om samenvattingen te kopen

Begin nu gratis

Laatst bekeken door jou


€16,96  1x  verkocht
  • (0)
In winkelwagen
Toegevoegd