Stormwater Management Inspector Prep Questions And Answers How does sheet flow to a vegetated filter strip or conserved open space work? Filter strips are vegetated areas that treat sheet flow delivered from adjacent impervious and managed turd areas by slowing runoff velocities and allowing ...

[Meer zien]

Voorbeeld 4 van de 43  pagina's

  • 13 oktober 2024
  • 43
  • 2024/2025
  • Tentamen (uitwerkingen)
  • Vragen en antwoorden
  • Storm Water Drainage
  • Storm Water Drainage
avatar-seller
Stormwater Management Inspector Prep
Questions And Answers

How does sheet flow to a vegetated filter strip or conserved open space work? Filter strips

are vegetated areas that treat sheet flow delivered from adjacent impervious and managed turd

areas by slowing runoff velocities and allowing sediment and attached pollutants to settle and/or

be filtered by the vegetation




Gravel diaphragm -pretreatment device


-maintains sheet flow

-not necessary if contributing drainage area is solely turf

-trench is 2 ft. wide and 1 ft. deep

-runs on same contour at top of filter strip

-drop at least 3 inches

-fabric between gravel and soil




Engineered level spreader -forebay: max. 3ft. deep, transition to 1 ft. at level spreader lip


-level spreader lip - concrete, wood, or prefabricated metal, with a well anchored footer, or other

accepted rigid, non-erodible material

-location: 3-6 inches above downstream natural grade to avoid turf buildup

, Stormwater Management Inspector Prep
Questions And Answers
-3ft. of VDOT #3 stone, underlain by filter fabric just below spreader

-vegetated receiving area must be stabilized




Construction sequence for conserved open space - no clearing, grading, heavy equipment


-protect area during construction

-prevent sediment discharge

-mark limits of disturbance

-drainage area stabilized

-grade with tracked vehicles

-install gravel diaphragm and/or level spreader

-mark filter boundaries

-keep vehicles out

-stockpile topsoil for later use

-divert construction runoff

-install gravel diaphragm and/or level spreader

-grade with tracked vehicles

-open to runoff once stabilized

, Stormwater Management Inspector Prep
Questions And Answers
Maintenance of Vegetated Filter Strips minimal; spring cleanup, regular mowing, check

dam repairs, and other methods of maintaining hydraulic efficiency




Grass channel design criteria -the bottom width of the channel should be between 4-8 feet

wide

-the channel side-slopes should be 3H:1V or flatter

-the maximum total contributing drainage area to any individual grass channel is 5 acres

-the longitudinal slope of the channel is <4%

-max flow velocity of channel must be <1ft/sec during a 1 inch storm event

-the dimensions of the channel should ensure that flow velocity is non-erosive during the 2-yr

and 10-yr design storm events and the 10-yr design flow is contained within the channel




Grass channel pretreatment -check dams


-tree check dams

-grass filter strip

-gravel or stone diaphragm

-gravel or stone flow spreaders

, Stormwater Management Inspector Prep
Questions And Answers
Check dams -Purpose: break-up slopes and increase time water stays in channel


max desired height 12-18 in

-averaging ponding depth: 12 in

-armoring may be needed downstream

-anchored into side slopes and bottom

-center weir to pass 10-year storm

-weep hole or similar drainage for dewatering, composed of wood/concrete/stone/other non-

erodible material




Grass Channel construction sequence -protect area during construction


-stabilize drainage area

-grade to final dimensions

-install check dams, pre-treatment

-soil compost amendments

-prepare planting holes




Soil Testing before Soil Compost Amendments 1st test:


-conducted every 5000 sq. ft. to determine soil properties

Voordelen van het kopen van samenvattingen bij Stuvia op een rij:

Verzekerd van kwaliteit door reviews

Verzekerd van kwaliteit door reviews

Stuvia-klanten hebben meer dan 700.000 samenvattingen beoordeeld. Zo weet je zeker dat je de beste documenten koopt!

Snel en makkelijk kopen

Snel en makkelijk kopen

Je betaalt supersnel en eenmalig met iDeal, creditcard of Stuvia-tegoed voor de samenvatting. Zonder lidmaatschap.

Focus op de essentie

Focus op de essentie

Samenvattingen worden geschreven voor en door anderen. Daarom zijn de samenvattingen altijd betrouwbaar en actueel. Zo kom je snel tot de kern!

Veelgestelde vragen

Wat krijg ik als ik dit document koop?

Je krijgt een PDF, die direct beschikbaar is na je aankoop. Het gekochte document is altijd, overal en oneindig toegankelijk via je profiel.

Tevredenheidsgarantie: hoe werkt dat?

Onze tevredenheidsgarantie zorgt ervoor dat je altijd een studiedocument vindt dat goed bij je past. Je vult een formulier in en onze klantenservice regelt de rest.

Van wie koop ik deze samenvatting?

Stuvia is een marktplaats, je koop dit document dus niet van ons, maar van verkoper UpperClass. Stuvia faciliteert de betaling aan de verkoper.

Zit ik meteen vast aan een abonnement?

Nee, je koopt alleen deze samenvatting voor €24,61. Je zit daarna nergens aan vast.

Is Stuvia te vertrouwen?

4,6 sterren op Google & Trustpilot (+1000 reviews)

Afgelopen 30 dagen zijn er 82191 samenvattingen verkocht

Opgericht in 2010, al 14 jaar dé plek om samenvattingen te kopen

Start met verkopen

Laatst bekeken door jou


€24,61
  • (0)
  Kopen