100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached
logo-home
INF3708 Exam Pack (Questions & Answers) with Great Notes. R50,54   Add to cart

Exam (elaborations)

INF3708 Exam Pack (Questions & Answers) with Great Notes.

 1 view  0 purchase

INF3708 Exam Pack (Questions & Answers) with Great Notes.100% TRUSTED Answers, guidelines, workings and references. MAY / JUNE 2016 EXAM REVISION 1 Please attempt the INF3708 exercises as part of your exam revision. Note that the revision of assignments & past exam papers are also very crucial f...

[Show more]

Preview 4 out of 161  pages

  • July 18, 2023
  • 161
  • 2022/2023
  • Exam (elaborations)
  • Questions & answers
All documents for this subject (33)
avatar-seller
LADHU
INF3708 Exam Pack (Questions &
Answers) with Great Notes.

, MAY / JUNE 2016 EXAM REVISION 1
Please attempt the INF3708 exercises as part of your exam revision. Note that the revision
of assignments & past exam papers are also very crucial for better performance. In fact,
proper understanding of the assignments & past exam papers almost guarantees a pass.


QUESTION 1:
The table below gives the estimated cash flow for three different projects (in rands R):
Year Project 1 Project 2 Project 3
0 - R 195 000 - R 160 000 - R 295 000
1 + R 15 000 + R 15 000 + R 30 000
2 + R 30 000 + R 15 000 + R 35 000
3 + R 55 000 + R 20 000 + R 50 000
4 + R 50 000 + R 35 000 + R 120 000
5 + R 55 000 + R 55 000 + R 110 000
6 + R 50 000 + R 90 000 + R 115 000

1. Calculate the Net Profit of each project. (3)
2. Based on your calculation of the Net Profit, identify which project you would
select to develop. Motivate your answer. (2)
3. Calculate of Return on Investment (ROI) of each of the projects given in the
table above. (3)
4. Based on your calculation of the ROI, identify which project you would
select to develop. (2)


QUESTION 2:
Consider the following project scenario and some questions related to it. The table below gives
the estimated cash flow for three different projects (in South African rands R):
Year Project 1 Project 2 Project 3
0 - R 170 000 - R 150 000 - R 280 000
1 - R 10 000 + R 5 000 + R 10 000
2 + R 20 000 + R 20 000 + R 30 000
3 + R 50 000 + R 30 000 + R 50 000
4 + R 50 000 + R 80 000 + R 120 000
5 + R 60 000 + R 90 000 + R 120 000
6 + R 60 000 - R 10 000 + R 120 000

1. Calculate the Net Profit of each project. (3)
2. Based on your calculation of the Net Profit, identify which project you would
select to develop. Motivate your answer. (2)
3. Calculate of Return on Investment (ROI) of each of the projects given in the
table above. (3)
4. Based on your calculation of the ROI, identify which project you would
select to develop. (2)

,QUESTION 3:
1. Consider the following list of tasks with dependencies and estimated durations reflected
in table Draw a CPM network (activity-on-arrow diagram) to illustrate the interaction
of activities. Include all the values in the nodes. Indicate the critical path on the diagram
Task Precedents Duration (weeks)
A - 4 2. Write down the critical path(s)
B - 3 using the letters of the tasks and
C A, B 5 calculate and write down the duration
D - 1 of the project. How many paths are
E C 5 there in total? Identify them all and
F D 2 write them down.
G E, F 5
H G 6


QUESTION 4:
1. Draw a complete Activity-on-arrow network diagram. Include the event number,
earliest date, latest date and slack on each node by completing both a forward and
backward pass. Clearly indicate the total duration and critical path.
Task Precedents Duration (days)
A None 8
B None 10
C None 8
D A 10
E A 16
F D, B 17
G C 18
H C 14
I F, G 9


QUESTION 5:
1. Draw a CPM network for the list of tasks in the table above to illustrate the interaction
of activities. Clearly identify the critical path and its duration.
Activity Precedents Duration (weeks)
A None 7
B A 10
C A 12
D B 3
E B 8
F B 7
G F 2
H D, E 5
I C 13
J C 6
K H 14
L E, F 5

, QUESTION 6:
1. Consider the following list of tasks with dependencies and estimated durations reflected
in table Draw a CPM network (activity-on-arrow diagram) to illustrate the interaction
of activities. Include all the values in the nodes. Indicate the critical path on the diagram
Task Precedents Duration (weeks)
A None 6
B None 2
C A 3
D B 2
E C 4
F D 1
G E, F 1
H G 6
I H 3
J H 1
K I, J 1
2. Write down the critical path(s) using the letters of the tasks and calculate and write
down the duration of the project. How many paths are there in total? Identify them all
and write them down.


QUESTION 7:
1. Consider the following activities with their precedents and durations. Draw a complete
Activity-on-arrow network diagram. Include the event number, earliest date, latest
date and slack on each node by completing both a forward and backward pass. Clearly
indicate the total duration and critical path.

Activity Precedents Duration (weeks)
A None 3
B A 4
C B 3
D B 10
E D 8
F D 4
G D 6
H C, E, F, G 8
I H 5
J H 5
K I 4
L J 2
M K, L 4

The benefits of buying summaries with Stuvia:

Guaranteed quality through customer reviews

Guaranteed quality through customer reviews

Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.

Quick and easy check-out

Quick and easy check-out

You can quickly pay through EFT, credit card or Stuvia-credit for the summaries. There is no membership needed.

Focus on what matters

Focus on what matters

Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!

Frequently asked questions

What do I get when I buy this document?

You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.

Satisfaction guarantee: how does it work?

Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.

Who am I buying this summary from?

Stuvia is a marketplace, so you are not buying this document from us, but from seller LADHU. Stuvia facilitates payment to the seller.

Will I be stuck with a subscription?

No, you only buy this summary for R50,54. You're not tied to anything after your purchase.

Can Stuvia be trusted?

4.6 stars on Google & Trustpilot (+1000 reviews)

79789 documents were sold in the last 30 days

Founded in 2010, the go-to place to buy summaries for 14 years now

Start selling
R50,54
  • (0)
  Buy now