Solution Manual for
Matching Supply with Demand An Introduction to Operations Management, 5th Edition Cachon
Chapter 2-19
Chapter 2
The Process View of the Organization
Q2.1 Dell
The following steps refer directly to Exhibit 2.1.
#1: For 2001, we find in Dell’s 10-k: Inventory = $400 (in million)
#2: For 2001, we find in Dell’s 10-k: COGS = $26,442 (in million)
26,442$ / year
#3: Inventory turns 66.105 turns per year
400$
40% per year
#4: Per unit Inventory cost 0.605% per year
66.105 per year
Q2.2. Airline
We use Little’s law to compute the flow time, since we know both the flow rate as well
as the inventory level:
Flow Time Inventory / Flow Rate 35 passengers / 255 passengers per hour 0.137 hours
8.24 minutes
Q2.3 Inventory Cost
(a) Sales $60,000,000 per year / $2000 per unit 30,000 units sold per year
Inventory $20,000,000/ $1000 per unit 20,000 units in inventory
Flow Time Inventory / Flow Rate 20,000/ 30,000 per year 2/ 3 year 8 months
Turns 1/ Flow Time 1/ (2/ 3 year) 1.5 turns per year
Note: we can also get this number directly by writing: Inventory turns COGS / Inventory
(b) Cost of Inventory: 25% per year /1.5 turns 16.66% . For a $1000 product, this would
make an absolute inventory cost of $166.66 .
Q2.4. Apparel Retailing
(a) Revenue of $100M implies COGS of $50M (because of the 100% markup).
Turns COGS/ Inventory $50M / $5M 10 .
(b) The inventory cost, given 10 turns, is 40%/10 4% . For a 30$ item, the inventory
cost is 0.4 $30 $1.20 per unit .
Q2.5. La Villa
(a) Flow Rate Inventory / Flow Time 1200 skiers /10 days 120 skiers per day
(b) Last year: on any given day, 10% (1 of 10) of skiers are on their first day of skiing
© McGraw Hill LLC. All rights reserved. No reproduction or distribution without the prior written consent of
McGraw Hill LLC.
, This year: on any given day, 20% (1 of 5) of skiers are on their first day of skiing
Average amount spent in local restaurants (per skier)
Last year 0.1 $50 0.9 $30 $32
This year 0.2 $50 0.8 $30 $34
% change ($34 $32) / $32 6.25% increase
Q2.6. Highway
We look at 1 mile of highway as our process. Since the speed is 60 miles per hour, it
takes a car 1 minute to travel through the process (flow time).
There are 24 cars on ¼ of a mile, i.e. there are 96 cars on the 1 mile stretch (inventory).
Inventory = Flow Rate * Flow Time: 96 cars = Flow Rate * 1 minute
Thus, the Flow Rate is 96 cars per minute, corresponding to 96*60 = 5760 cars per hour.
Q2.7. Strohrmann Baking
The bread needs to be in the oven for 12 minutes (flow time). We want to produce at a
flow rate of 4000 breads per hour, or 4000/60 = 66.66 breads per minute.
Inventory = Flow Rate * Flow Time: Inventory = 66.66 breads per minute* 12 minutes
Thus, Inventory = 800 breads, which is the required size of the oven.
Q2.8. Mt Kinley Consulting
We have the following information available from the question:
Level Inventory (number of consultants at Flow Time (time spent at that
that level) level)
Associate 200 4 years
Manager 60 6 years
Partner 20 10 years
(a) We can use Little’s law to find the flow rate for associate consultants: Inventory =
Flow Rate * Flow Time; 200 consultants = Flow Rate * 4 years; thus, the flow rate is
50 consultants per year, which need to be recruited to keep the firm in its current size
(note: while there are also 50 consultants leaving the associate level, this says nothing
about how many of them are dismissed vs how many of them are promoted to
Manager level).
(b) We can perform a similar analysis at the manager level, which indicates that the flow
rate there is 10 consultants. In order to have 10 consultants as a flow rate at the
manager level, we need to promote 10 associates to manager level (remember, the
firm is not recruiting to the higher ranks from the outside). Hence, every year, we
dismiss 40 associates and promote 10 associates to the manager level (the odds at that
level are 20%)
© McGraw Hill LLC. All rights reserved. No reproduction or distribution without the prior written consent of
McGraw Hill LLC.
, Now, consider the partner level. The flow rate there is 2 consultants per year (obtained
via the same calculations as before). Thus, from the 10 manager cases we evaluate every
year, 8 are dismissed and 2 are promoted to partner (the odds at that level are thereby also
20%).
In order to find the odds of a new hire to become partner, we need to multiply the
promotion probabilities: 0.2*0.2 = 0.04. Thus, a new hire has a 4% chance of making it to
partner.
Q2.9. Major US Retailers
a. Product stays on average for 31.9 days in Costco’s inventory
b. Costco has for a $5 product an inventory cost of $0.1311 which compares to a
$0.2049 at Wal-Mart
Q2.10. McDonald’s
a. Inventory turns for McDonald’s were 92.3. They were 30.05 for Wendy’s.
b. McDonald’s has per unit inventory costs of 0.32%, which for a 3$ meal about
$0.00975 . That compares to 0.998% at Wendy’s where the cost per meal is $0.0299 .
Q2.11. BCH
I = 400 associates, T = 2 years. R I / T 400 associates / 2 yrs 200 associates / yr .
Q2.12. Kroger
Turns R / I 12.3
Matching Supply with Demand: An Introduction to Operations Management
5e
Solutions to Chapter Problems
Chapter 3
Understanding the Supply Process: Evaluating Process Capacity
Q3.1 Process Analysis with One Flow Unit
(a) Capacity of the three resources in units per hour are 60 2 /10 12 , 60 1/ 6 10 ;
60 3 /16 11.25 . The bottleneck is the resource with the lowest capacity, which is
resource 2.
(b) The process capacity is the capacity of the bottleneck, which is 10 units/hr .
(c) If demand 8 units / hr , then the process is demand constrained and the flow rate is
8 units/hr
(d) Utilization = Flow Rate / Capacity . For the three resources they are 8 /12 , 8 /10 , and
8 /11.25 .
© McGraw Hill LLC. All rights reserved. No reproduction or distribution without the prior written consent of
McGraw Hill LLC.
, Q3.2 Process Analysis with Multiple Flow Units
a) Bottleneck is resource 3 because it has the highest implied utilization of 125%. The
demands per hour of the three products are 5 , 6.25 and 7.5 . The
total minutes of work demanded per hour at resource 1 is 5 × 5 + 6.25 * 5 + 7.5 * 5 =
93.75. Two workers at resource 1 produce 2 * 60 = 120 min of work per hour. So
resource 1’s utilization is 93.75 /120 0.78 . Utilization at the other resources are
similarly evaluated.
b) The capacity of resource 3 is 60 /15 4 units per hour. Given the ratio of units produced
must be 4 to 5 to 6, the process can produce 4 units/ hr of A, 5 units / hr of B and
6 units / hr of C.
Q3.3. Cranberry
Cranberries arrive at a rate of 150 barrels per hour. They get processed at a rate of 100 barrels
per hour. Thus, inventory accumulates at a rate of 150-100 = 50 barrels per hour. This happens
while trucks arrive, i.e. from 6am to 2pm. The highest inventory level thereby is 8h*50 barrels
per hour = 400 barrels. From these 400 barrels, 200 barrels are in the bins, the other 200 barrels
are in trucks.
(a) 200 barrels
(b) From 2pm onwards, no additional cranberries are received. Inventory gets depleted at a rate
of 100 barrels per hour. Thus, it will take 2h until the inventory level has dropped to 200
barrels, at which time all waiting cranberries can be stored in the bins (no more truck
waiting)
(c) It will take another 2 hours until all the bins are empty
(d) Since the seasonal workers only start at 10:00am, the first 4 hours of the day we accumulate
4hours * 50barrels per hour = 200 barrels. For the remaining time that we receive incoming
cranberries, our processing rate is higher (125 barrels per hour). Thus, inventory only
accumulates at a rate of 25 (150-125 barrels per hour). Given that this happens over 4 hours,
we get another 100 barrels in inventory. At 2pm, we thereby have 300 barrels in inventory.
After 2pm, we receive no further cranberries, yet we initially process cranberries at a rate of
125 barrels per hour. Thus, it only takes 100 barrels /125 barrels/hour 0.8 hours 48 minutes
until all bins are empty. From then, we need another 2h until the bins are empty.
Q3.4. Western Pennsylvania Milk
We start the day with 25,000 gallons of milk in inventory. From 8am onwards, we produce 5,000
gallons, yet we ship 10,000 gallons. Thus inventory is depleted at a rate of 5000 gallons per hour,
which leaves us without milk after 5 hours (at 1pm). From then onwards, clients will have to
wait. This situation gets worse and worse and by 6pm (last client arrives), we are short 25,000
gallons.
(a) 1pm
(b) Clients will stop waiting when we have worked off our 25,000 gallon backlog that we are
facing at 6pm. Since we are doing this at a rate of 5,000 gallon per hour, clients will stop
waiting at 11pm (after 5 more hours).
(c) At 6pm, we have a backlog of 25,000 gallons, which is equivalent to 20 trucks
(d) The waiting time is the area in the triangle