Identify typical team member of the Cx Team. Correct Ans - 1. Owner
2. End user
3. architect
4. electrical engineer
5. mechanical engineer
6. commissioning authority
7. controls contractor
8. mechanical contractor
9. electrical contractor
10. sheet metal contractor
11. TAB agency
12. General or construction manager
13. owners O&M staff
Comprehensive Commissioning Correct Ans - 1. commissioning starts
at the inception of a building project during the pre-design phase, and
continues through the post-acceptance phase.
2. provides an opportunity to cultivate a quality management focus among all
design and construction team members as they become involved with the
project
Which Chapter of the ACG guideline identifies detailed methodology for
Comprehensive HVAC Commissioning? Correct Ans - Chapter 5
What are the Comprehensive Commissioning phases? Correct Ans -
Pre-design
Design
Construction
Acceptance
Post Acceptance
Comprehensive Commissioning: Pre-design phase Correct Ans - 1.
Commissioning established as integral part of project
2. The owner selects the commissioning authority
3. Develop the scope of commissioning
4. Commissioning authority reviews design intent document
, Comprehensive Commissioning Design phase Correct Ans - 1. Review
design to ensure it accommodates commissioning
2. Write commissioning specifications defining contractor
responsibilities
3. Commissioning authority writes the commissioning plan
4. Establish the project schedule
Comprehensive Commissioning Construction phase Correct Ans - 1.
Commissioning authority reviews contractor submittals
2. Commissioning authority updates commissioning plan
3. Commissioning process is coordinated—through project
schedule, commissioning plan and commissioning plan
and commissioning meetings
4. Carry out and document system verification checks
5. Carry out the document equipment and system start-ups
6. TAB agency completes and documents TAB work
Comprehensive Commissioning Acceptance phase Correct Ans - 1.
Carry out FPTs on all HVAC systems
2. Train the O&M staff for effective, ongoing operations and maintenance of all
systems
3. Provide full documentation
Comprehensive Commissioning Post-Acceptance phase Correct Ans -
1. Correct any deficiencies, carry out required re-testing
2. Carry out any required "off-season" tests
3. Update documentation as required
Identify the Comprehensive HVAC commissioning organizational structure for
Plan & Spec Correct Ans -
During commissioning what statements identify the CxA's role? Correct
Ans - 1. Authority leads the commissioning process, and works
cooperatively with the designers and contractors, but always in the owner's
interest
2. Facilitates communication and coordination among designers, contractors
and suppliers.
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through EFT, credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying this summary from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller LeCrae. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy this summary for R186,16. You're not tied to anything after your purchase.