IRC (International Residential Code) -Correct Answer Created to serve as a complete, comprehensive code regulating the construction of single-family, two-family and buildings consisting of three or more townhouse units.
First 2 chapters of code book are -Correct Answer Administrative
Plans or...
MICHIGAN BUILDERS LICENSE EXAM
(GENERAL CONTRACTOR) 2024-2025
ATUAL EXAM
IRC (International Residential Code) -Correct Answer ✔Created to serve as a complete,
comprehensive code regulating the construction of single-family, two-family and
buildings consisting of three or more townhouse units.
First 2 chapters of code book are -Correct Answer ✔Administrative
Plans or supporting documents are almost always required by the controlling authority
prior to issuing a permit. T or F -Correct Answer ✔True
Does the building official have the authority to render interpretations of the code? -
Correct Answer ✔Yes
None of the following require a permit, EXCEPT:
sidewalks and driveways
tiling
an 8 foot fence
playground equipment -Correct Answer ✔8 foot fence.
Tables and illustrations are always supported by information found in the written code
and footnotes. T or F -Correct Answer ✔False
The amount of evenly distributed weight imposed by inhabitants, goods and removable
objects on a floor or roof system is referred to as -Correct Answer ✔Live load.
If a code requirement is in the book, it is both acceptable and enforceable by the code
official. T or F -Correct Answer ✔True.
Illustrations are typically referred to as -Correct Answer ✔Figures.
Generally speaking, the building official's job is to -Correct Answer ✔Determine that
buildings are built to the minimum enforceable standard.
It is required that all manufacturer instructions be at the jobsite at the time of inspection.
T or F -Correct Answer ✔True.
All of the following are not considered habitable spaces EXCEPT:
bathrooms
kitchens
MICHIGAN BUILDERS LICENSE EXAM
,MICHIGAN BUILDERS LICENSE EXAM
storage spaces
closets -Correct Answer ✔Kitchen.
Bathrooms must be provided with an aggregate glazing area no less than _____ square
feet, half of which must be openable. -Correct Answer ✔3.
The maximum height of an egress window above the floor is -Correct Answer ✔44
inches.
A basement bedroom must have an egress window with a clear opening of at least
______ square feet. -Correct Answer ✔5.7 sq ft.
At least one side-hinged exit door must be in each dwelling unit, and must be _____
feet wide. -Correct Answer ✔3.
A porch more than _____ inches above grade must be provided with 36" guards. -
Correct Answer ✔30 inches.
Wall and ceiling finishes shall have a flame-spread classification of no more than
______ . -Correct Answer ✔200.
According to code, concrete must reach at least 70% of it's ability within
____________days. -Correct Answer ✔7 days.
A stud used for a non-bearing partitions may not be notched more than ____% of the
stud width. -Correct Answer ✔40%.
The Michigan Uniform Energy code applies to new buildings as well as -Correct Answer
✔Additions, alterations, renovation and repairs.
___________ is a measure of how well the window or door assembly conducts heat.
The lower the number, the better insulation the assembly will provide. -Correct Answer
✔U-factor.
Energy losses from recessed lighting fixtures can often reach ___% of the total thermal
loss of a ceiling. -Correct Answer ✔50%.
Michigan requires a minimum thermal resistance of ____________for mechanical
system piping. -Correct Answer ✔R-3.
Oversized HVAC equipment has a higher initial cost, a higher operating cost, provides
less comfort, and shorter life expectancy. T or F -Correct Answer ✔True.
MICHIGAN BUILDERS LICENSE EXAM
,MICHIGAN BUILDERS LICENSE EXAM
_______ is the compliance route that applies Table 402.1.1 to building envelope
components, and is considered the most simple. -Correct Answer ✔Prescriptive Path.
___________ can be used to satisfy U-factor and SHGC requirements. -Correct Answer
✔Area weighted averages.
Recessed lights must be _____ rated. -Correct Answer ✔IC (Insulation Contact)
Up to 15 square feet of glazing per dwelling unit is exempted from U-value
requirements. T or F -Correct Answer ✔True.
The 2009 IECC requires a permanent certificate posted on the electrical distribution
panel. The certificate shall be completed by the builder or -Correct Answer ✔Registered
design professional.
One hurdle contractors face when bidding for an energy efficient project is choosing
materials that fit the design, and also meet -Correct Answer ✔State energy code
requirements.
Historically significant buildings are not exempt from code changes. T or F -Correct
Answer ✔False.
Insulation products (blown and sprayed) must be documented with: -Correct Answer
✔R-value
Settled thickness
Manufacturer name
The new Michigan codes took effect in -Correct Answer ✔March 2011.
Below grade walls are insulated from the top of the basement wall down to _____ below
grade, or the basement floor, whichever is less. -Correct Answer ✔10.
The _______ is the combined Solar Heat Gain Coefficient of all the glazed fenestration
products in the building. -Correct Answer ✔Area weighted average.
Plans and specifications must be detailed in regards to: -Correct Answer ✔Thermal
insulation R-values
Design criteria
Equipment systems
In Michigan, the residential energy code is based on the _____ IECC, with certain
amendments. -Correct Answer ✔2009.
MICHIGAN BUILDERS LICENSE EXAM
, MICHIGAN BUILDERS LICENSE EXAM
___________ is the rate of air infiltration in the presence of a specific pressure
differential. -Correct Answer ✔Air leakage.
Air leakage is the random movement of air into and out of ________ through cracks and
holes. -Correct Answer ✔Windows
Attic access hatches
Recessed lights
R-values for insulation and fenestration requirements by component can be found in -
Correct Answer ✔Table 402.1.1
2009 IECC
IECC -Correct Answer ✔International Energy Conservation Code
The _____________ compliance method allows for more innovative construction
techniques like SIPs or Advanced Framing. -Correct Answer ✔U-factor and UA
alternatives.
R-30 is permitted in vaulted ceilings, but is limited to -Correct Answer ✔500 sq feet
Floor insulation must be installed to maintain permanent and continuous contact with
the underside of the subfloor decking. T or F -Correct Answer ✔True.
Michigan falls into climate zones -Correct Answer ✔5, 6 and 7.
It is permissible for supply ducts to be run through the framing cavities of a residential
building. T or F -Correct Answer ✔False.
__________ means an electrical fixture has been tested and listed as suitable for
installation in a cavity where the fixture may come in contact with insulation. -Correct
Answer ✔IC rated (Insulation Contact)
According to the Dept. of Energy, improved energy codes could reduce CO2 emissions
by -Correct Answer ✔3%.
Attic insulation markers must be installed every _____ square feet. -Correct Answer
✔300 sq ft.
Buildings that are exempted from the new regulations are those with very low energy
use or ones that are neither heated or cooled. T or F -Correct Answer ✔True.
A contractor needs to remove a non-load bearing wall, does he need to pull a permit? -
Correct Answer ✔Yes.
MICHIGAN BUILDERS LICENSE EXAM
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through EFT, credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying this summary from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller PossibleA. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy this summary for R280,85. You're not tied to anything after your purchase.