TEST BANK For Information Technology Project Management 9th Edition by Kathy Schwalbe, Verified Chapters 1 - 13, Complete Newest Version
TEST BANK For Information Technology Project Management 9th Edition Kathy Schwalbe, Verified Chapters
FULL TEST BANK For Information Technology Project Management 9th Edition by Kathy Schwalbe Latest Update Graded A+
All for this textbook (49)
Written for
Project Management 9th Edition
Project Management 9th Edition
Seller
Follow
AMAZONEDUCATER
Reviews received
Content preview
Complete Test Bank
For Information Technology
Project Management 9th Edition
By Kathy Schwalbe
, Test Bank For, Information Technology Project
Management 9th Edition
By Kathy Schwalbe
True / False
1. Until The 1980s, Project Management Primarily Focused On Providing Schedule And Resource Data
To TopManagement In The Military, Computer, And Construction Industries.
A. True
B. False
Answer: True
Rationale: Feedback: Until The 1980s, Project Management Primarily Focused On
ProvidingSchedule And Resource Data To Top Management In The Military,
Computer, And Construction Industries. Today’s Project Management Involves
Much More, And People In Every Industry And Every Country Manage
Projects.
Points: 1
Difficulty: Difficulty: Easy
References: P.2
Learning Objectives: Info.Schw.14.1 - Lo: 1-1
National Standards: United States - Busprog: Technology
Topics: Introduction
Keywords: Bloom's: Knowledge
2. A Difference Between Operations And Projects Is That Operations End When Their Objectives
Have BeenReached, Whereas Projects Do Not.
A. True
B. False
Answer: False
Rationale: Feedback: Projects Are Different From Operations In That They End When
TheirObjectives Have Been Reached Or The Project Has Been Terminated.
Points: 1
Difficulty: Difficulty: Moderate
References: P.4
Learning Objectives: Info.Schw.14.2 - Lo: 1-2
National Standards: United States - Busprog: Analytic
Topics: What Is A Project?
Keywords: Bloom's: Comprehension
,3. Every Project Should Have A Well-Defined Objective.
A True
.
, B. False
Answer: True
Rationale: Feedback: A Project Has A Unique Purpose. Every Project Should Have A Well-
DefinedObjective.
Points: 1
Difficulty: Difficulty: Easy
References: P.6
Learning Objectives: Info.Schw.14.2 - Lo: 1-2
National Standards: United States - Busprog: Analytic
Topics: What Is A Project?
Keywords: Bloom's: Knowledge
4. Projects Should Be Developed In Increments.
A. True
B. False
Answer: True
Rationale: Feedback: A Project Is Developed Using Progressive Elaboration. Projects Are
OftenDefined Broadly When They Begin, And As Time Passes, The Specific
Details Of The Project Become Clearer. Therefore, Projects Should Be Developed
In Increments.
Points: 1
Difficulty: Difficulty: Moderate
References: P.6
Learning Objectives: Info.Schw.14.2 - Lo: 1-2
National Standards: United States - Busprog: Analytic
Topics: What Is A Project?
Keywords: Bloom's: Comprehension
5. Resources In A Project Should Be Used Effectively Because They Are Limited.
A. True
B. False
Answer: True
Rationale: Feedback: A Project Requires Resources, Often From Various Areas.
Resources,However, Are Limited And Must Be Used Effectively To Meet
Project And Other Corporate Goals.
Points: 1
Difficulty: Difficulty: Moderate
References: P. 7
Learning Objectives: Info.Schw.14.2 - Lo: 1-2
National Standards: United States - Busprog: Analytic
Topics: What Is A Project?
Keywords: Bloom's: Comprehension
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through EFT, credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying this summary from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller AMAZONEDUCATER. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy this summary for R297,24. You're not tied to anything after your purchase.