"as-built" - answer According to the BCES specs, a set of drawings is to be maintained
at the jobsite for the purpose of recording the final size, location and interrelation of
work as the job progresses. This set of __ drawings is used to indicate the location of
equipment, including concealed conduit and equipment.
specific to a particular project - answer Written specifications are __.
innerduct – answer BCES specs require that all fiber optic backbone cable shall be
installed in __.
more information about some aspect of the project - answer On a construction project,
an RFI is used to obtain __.
electrical contractor - answer According to the BCES specs, damage repairs to the
factory painted finish of electrical equipment is the responsibility of the __.
The architect provides written approval - answer You can deviate from the specs if __.
installed in conduit - answerThe BCES spec require cafeteria sound system cable
installed above sheetrock ceiling to be __.
6 - answerThe BCES Specs require that convenience receptacles be installed at a
height of __ inches above counter tops or back splashes.
the project manager - answerOn a construction project, PM is the designation for ___.
electrical - answerPrior to construction, the __ electrical contractor is responsible for
verifying that conductors have sufficient ampacity to serve equipment furnished by the
MC.
8'-0" - answerThe concrete contractor will build the BCES light pole bases so that the
bottom of the concrete is at a depth of __ below the top of grade or paving.
44' 7 3/4" - answerYou are going to set a 1900 box north of column line F.5 on the
bottom of the 1st bar joist east of the beam on column line 11. Then you are going to
run EMT due east on the bottom of the bar joists and hit joists that are installed as
shown and the 1900 boxes are centered under the bar joists, you should need __ of
EMT to run between the two boxes in a straight line.
, 120.00 - answerAdjacent to the BCES property, the width of the right-of-way across FM
Hwy 646 is __ feet.
1" = 50' - answerThe scale used on the BCES utility plan is __.
30 - answerRe: S1.2. A typical section is cut through the exterior wall. See 1/S4.1.
Conduit will be run underground out to the site lighting. It will originate within the
building. It will be routed between the piers. The top of the conduit must be at least __
below the finished floor to pass under the grade beams.
16 - answerThe height of the beam along column line F.5 that spans between columns
11 & 12.9 is __".
unsuitable - answerDirt (soil) on a site may be required to be removed and replaced if
the soil is deemed __.
1" =50" - answerThe scale used on the BCES Survey drawing in the plans is __
True - answerRE: S1.2. A typical section is cut through the exterior wall. See 1/S4.1.
The floor slab will be 6" thick.
5 1/2 - answerRe: S1.2. A typical section is cut through the exterior wall. See 1/S4.1.
There will be a " -wide brick ledge along the top of the grade beam.
I or II only - answerA benchmark is typically placed by a __ firm.
I. government agency
II. private survey
III. earth moving
all of these - answerA site plan is used to __.
a. locate lot lines
b. place the building
c. establish elevations
d. all of these
below - answerRe: S1.2 A typical section is cut through the exterior wall. See 1/S4.1/
Before the slab is poured, a sand cushion is spread __ the vapor barrier.
16 - answerFor BCES wall construction, __guage studs are specified to be used.
6" studs, 2-sided with single layer 5/8" rock, and 1/2 rock added to one side(studs and
rock are deck high) - answerThe south wall of Room B132 is constructed of __.
I only - answerWhen conduit runs through a BCES type __ wall above the ceiling, the
conduit must be "fire-caulked" where it passes through the wall.
I. E
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through EFT, credit card or Stuvia-credit for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying this summary from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller julianah420. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy this summary for R263,80. You're not tied to anything after your purchase.